Sundridge 11kV Substation

Sundridge 11kV Substation is an 11 kV primary substation in England, United Kingdom, with 6.7 MVA of demand headroom and 23 MVA of generation headroom, operated by South Eastern Power Networks plc (UK Power Networks, South East England licence area).

Map: where Sundridge 11kV lies
51.2800, 0.1339 on OpenStreetMap

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationEnglandUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Grid operatorSouth Eastern Power Networks plc (UK Power Networks, South East England licence area)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Demand headroom6.7 MVAUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Generation headroom23 MVAUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Firm capacity24 MVAUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
LevelPrimary substationUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Voltage11 kVUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Coordinates51.2800, 0.1339UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026

Research on this substation and the land around it.Its headroom, connection queue and congestion, who owns the land around it, and an introduction to those owners.

Nearby

Within 50 km of this substation: 352 grid connections (242 operating, 2,458 MW), 349 power plants (138 operating, 6,807 MW), 97 data centers (1 operating, 88 MW) and 1 transmission line, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Greatness Quarry Landfill 451338 grid connectionGrid connection2.2 MWOperating4.9 km
Pratts Bottom grid connectionGrid connection45 MWPlanned7.4 km
Bough Beech Treatment Works grid connectionGrid connection1.8 MWOperating7.9 km
Gaywood FarmPower plant7.5 MWCancelled8.9 km
Biggin Hill Airport, Main Road - Solar PV ArrayPower plant12 MWUnder construction9.1 km
Skinners FarmPower plant6 MWCancelled9.6 km
Pulsant South LondonData center——19 km
Goldman Sachs data center, East GrinsteadData center——20 km
Unit 3Data center——21 km

Grid operator and place