Substation · England, United Kingdom
Stody Primary 11kV Substation
Stody Primary 11kV Substation is an 11 kV primary substation in England, United Kingdom, with 0.6 MVA of demand headroom and 13 MVA of generation headroom, operated by Eastern Power Networks plc (UK Power Networks, East England licence area).
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | England | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
| Grid operator | Eastern Power Networks plc (UK Power Networks, East England licence area) | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
| Demand headroom | 0.6 MVA | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
| Generation headroom | 13 MVA | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
| Firm capacity | 13 MVA | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
| Level | Primary substation | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
| Voltage | 11 kV | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
| Coordinates | 52.8775, 1.0447 | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
Research on this substation and the land around it.Its headroom, connection queue and congestion, who owns the land around it, and an introduction to those owners.
Nearby
Within 50 km of this substation: 165 power plants (66 operating, 3,578 MW), 102 grid connections (71 operating, 1,226 MW), 2 transmission lines and 1 data center, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Edgefield Hall grid connection | Grid connection | 1.4 MW | Operating | 3.3 km |
| Edgefield Sand & Gravel Works grid connection | Grid connection | 1.3 MW | Operating | 3.4 km |
| Snettisham Solar Farm | Power plant | 2.7 MW | Operating | 8.2 km |
| Guestwick | Power plant | 12 MW | Cancelled | 8.4 km |
| Heydon Road, Heydon - Solar PV Panels | Power plant | 30 MW | Permitted | 8.8 km |
| Pond Farm grid connection | Grid connection | 3 MW | Operating | 9.2 km |
| Norwich to Tilbury | Transmission line | — | Planned | 37 km |
| Kings Lynn B Connection Project | Transmission line | — | Permitted | 49 km |
| Longmarsh Green Energy | Data center | — | Planned | 49 km |
Grid operator and place
Grid connections attached to this substation
More from Eastern Power Networks plc
- Canvey Primary 11kVsubstation
- Thorley Primary 11kVsubstation
- Peterborough South Grid 11kVsubstation
- Westbury Primary 11kVsubstation
- Laxfield Primary 11kVsubstation
- Fulbourn Grid 33kVsubstation
- Earlham Grid 33kVsubstation
- Hunstanton Primary 11kVsubstation
Other substations in England
Data on this page
- Contains public sector information licensed under the Open Government Licence v3.0. DESNZ Renewable Energy Planning Database (REPD), Open Government Licence v3.0.
- Contains public sector information licensed under the Open Government Licence v3.0. Planning Inspectorate: National Infrastructure Projects, Open Government Licence v3.0.
- UK Power Networks. UK Power Networks open data portal, CC BY 4.0.