Substation · England, United Kingdom
Nacton Primary 11kV Substation
Nacton Primary 11kV Substation is an 11 kV primary substation in England, United Kingdom, with 8.6 MVA of demand headroom and 20.7 MVA of generation headroom, operated by Eastern Power Networks plc (UK Power Networks, East England licence area).
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | England | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
| Grid operator | Eastern Power Networks plc (UK Power Networks, East England licence area) | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
| Demand headroom | 8.6 MVA | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
| Generation headroom | 20.7 MVA | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
| Firm capacity | 24 MVA | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
| Level | Primary substation | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
| Voltage | 11 kV | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
| Coordinates | 52.0320, 1.2028 | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
Research on this substation and the land around it.Its headroom, connection queue and congestion, who owns the land around it, and an introduction to those owners.
Nearby
Within 50 km of this substation: 180 power plants (66 operating, 2,784 MW), 131 grid connections (78 operating, 1,326 MW) and 3 transmission lines, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Sewage Treatment Works - Phs Ii grid connection | Grid connection | 2.4 MW | Operating | 2.1 km |
| Ipswich Hospital Energy Centre | Power plant | 2.6 MW | Operating | 2.8 km |
| Foxhall Landfill Site | Power plant | 1.2 MW | Operating | 4.8 km |
| Npower Limited - Foxhall Landfill Site grid connection | Grid connection | 1.18 MW | Operating | 5.3 km |
| Pannington Hall | Power plant | 3 MW | Cancelled | 5.7 km |
| Solar 22.5 MW grid connection at Felixstowe Grid 33kV | Grid connection | 22.5 MW | Planned | 5.7 km |
| Bramford to Twinstead | Transmission line | — | Permitted | 24 km |
| LionLink Interconnector | Transmission line | — | Planned | 29 km |
| Sea Link | Transmission line | — | Planned | 47 km |
Grid operator and place
More from Eastern Power Networks plc
- Canvey Primary 11kVsubstation
- Thorley Primary 11kVsubstation
- Peterborough South Grid 11kVsubstation
- Westbury Primary 11kVsubstation
- Laxfield Primary 11kVsubstation
- Fulbourn Grid 33kVsubstation
- Earlham Grid 33kVsubstation
- Hunstanton Primary 11kVsubstation
Other substations in England
Data on this page
- Contains public sector information licensed under the Open Government Licence v3.0. DESNZ Renewable Energy Planning Database (REPD), Open Government Licence v3.0.
- Contains public sector information licensed under the Open Government Licence v3.0. Planning Inspectorate: National Infrastructure Projects, Open Government Licence v3.0.
- UK Power Networks. UK Power Networks open data portal, CC BY 4.0.