Substation · England, United Kingdom
Longsight
Longsight is a substation in England, United Kingdom.
We hold more on this substation.Demand headroom, generation headroom, grid operator, location, level, fed from and voltage: available on request.
Request this dataFacts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Name in the source | LONGSIGHT | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Location | Available on request | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Grid operator | Available on request | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Demand headroom | Available on request | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Generation headroom | Available on request | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Level | Available on request | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Fed from | Available on request | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Voltage | Available on request | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Coordinates | 53.4617, -2.2164 | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
Know more about this substation? Ask us.
Nearby
Within 50 km of this substation: 393 grid connections (218 operating, 1,999 MW), 378 power plants (101 operating, 1,032 MW), 21 data centers and 3 gas storage facilities, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Octagon House EC2 grid connection | Grid connection | 6.72 MW | Planned | 0.1 km |
| Octagon House grid connection | Grid connection | 6.7 MW | Planned | 0.1 km |
| Manchester Royal Infirmary grid connection | Grid connection | 6.4 MW | Operating | 0.6 km |
| Equinix MA1 | Data center | — | — | 1.3 km |
| Equinix MA4 | Data center | — | — | 1.4 km |
| Ardwick Railway Goods Yard Incinerator (Newhaven EFW Plant) | Power plant | 33.5 MW | Operating | 1.6 km |
| Lunar 1&2 | Data center | — | — | 2.1 km |
| City Football Academy, Ashton New Road - Solar panels | Power plant | 3.38 MW | Operating | 2.8 km |
| City Football Academy - Solar Panels | Power plant | 1.12 MW | Permitted | 2.9 km |
Place
Grid connections attached to this substation
Other substations in England
Data on this page
- Contains public sector information licensed under the Open Government Licence v3.0. DESNZ Renewable Energy Planning Database (REPD), Open Government Licence v3.0.
- SP Electricity North West, via Northern Powergrid Open Data. SP Electricity North West open data portal, CC BY 4.0.
- © OpenStreetMap contributors. OpenStreetMap data centers, ODbL 1.0.