RARE CONTEXT Request research

Substation · England, United Kingdom

Benhall Primary 11kV Substation

Benhall Primary 11kV Substation is an 11 kV primary substation in England, United Kingdom, with 5.9 MVA of demand headroom and 11.3 MVA of generation headroom, operated by Eastern Power Networks plc (UK Power Networks, East England licence area).

Map: where Benhall Primary 11kV lies
52.2098, 1.4702 on OpenStreetMap

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationEnglandUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Grid operatorEastern Power Networks plc (UK Power Networks, East England licence area)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Demand headroom5.9 MVAUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Generation headroom11.3 MVAUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Firm capacity13 MVAUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
LevelPrimary substationUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Voltage11 kVUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Coordinates52.2098, 1.4702UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026

Research on this substation and the land around it.Its headroom, connection queue and congestion, who owns the land around it, and an introduction to those owners.

Nearby

Within 50 km of this substation: 180 power plants (48 operating, 3,261 MW), 122 grid connections (70 operating, 1,361 MW) and 3 transmission lines, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Parham Airfield (Great Glenham)Power plant17.5 MWOperating4.1 km
LionLink InterconnectorTransmission line—Planned4.4 km
Parham Airfield / Great Glenham grid connectionGrid connection15 MWOperating4.5 km
New Road Solar FarmPower plant49.9 MWCancelled4.5 km
Town Farm Lane grid connectionGrid connection15 MWPlanned4.6 km
Town Farm - Solar panelsPower plant21 MWPermitted5.0 km
Dennington Hall Farm grid connectionGrid connection20 MWPlanned5.3 km
Norwich to TilburyTransmission line—Planned43 km
Bramford to TwinsteadTransmission line—Permitted48 km

Grid operator and place

More from Eastern Power Networks plc

Candidate sites around this substation

1 site of land near Benhall Primary 11kV has it as nearest substation. Each site page gives its area, its distance to the substation and its site score; owners are on request.

Other substations in England

All 2633 substations in England, United Kingdom

Data on this page