Powered land · North Rhine-Westphalia

50 ha site at Gemarkung Eickelborn, Flur 5, Flurstück 75

A candidate site of 49.9 ha in North Rhine-Westphalia, made up of 9 cadastral parcels, mostly farmland. It lies 0.7 km from the 110 kV substation Schoneberg (Westnetz GmbH). The nearest transmission substation, Umspannungsanlage Uentrop (380 kV), is 14.3 km away, where the grid development plan lists 2 measures.

Owner, grid capacity and planning status on request.We do not publish owners: the German land register (Grundbuch) is not public. Ask us and we find out who owns these parcels, the free capacity at the nearest substation and the zoning that applies, and whether the site is available.

Request owner, grid and planning

Facts

Every value links to its source. Licences and last-checked dates are per row.

FactValueSource
Area49.9 ha (the official areas of its parcels added up)Rare Context powered-land sites · ODbL 1.0 · checked 24 Oct 2026
Cadastral parcels9 (largest: Gemarkung Eickelborn, Flur 5, Flurstück 75)ALKIS Nordrhein-Westfalen (open cadastre) · dl-de/zero-2-0 · checked 24 Oct 2026
Land useFarmland (Landwirtschaft) (81% of the area, as the cadastre records it)Rare Context powered-land sites · ODbL 1.0 · checked 24 Oct 2026
LocationNorth Rhine-WestphaliaRare Context powered-land sites · ODbL 1.0 · checked 24 Oct 2026
Coordinates51.6473, 8.2022 (a point on the largest parcel)Rare Context powered-land sites · ODbL 1.0 · checked 24 Oct 2026
Nearest substationSchoneberg (0.7 km, site edge to substation fence)Rare Context powered-land sites · ODbL 1.0 · checked 24 Oct 2026
Substation voltage110 kVOpenStreetMap power infrastructure (Overpass) · record · ODbL 1.0, © OpenStreetMap contributors · checked 24 Oct 2026
Substation operatorWestnetz GmbHOpenStreetMap power infrastructure (Overpass) · record · ODbL 1.0, © OpenStreetMap contributors · checked 24 Oct 2026
Nearest transmission substationUmspannungsanlage Uentrop (14.3 km from the nearest parcel, 380 kV, Amprion GmbH)Rare Context powered-land sites · ODbL 1.0 · checked 24 Oct 2026
Planned at that substationMSCDN (1x) (due 2032); Short-circuit strength upgrade (due 2037) (Netzentwicklungsplan)Netzentwicklungsplan Strom: digital project library · CC BY 4.0 · checked 24 Oct 2026

How it compares

#353 of 632 sites in North Rhine-Westphalia and #2,876 of 4,863 in Germany by site score. Larger than 13% of the sites in North Rhine-Westphalia. Closer to its substation than 72% of them.

PartThis sitePointsOf
Area49.9 ha15.735
Distance to the substation0.7 km22.835
Substation voltage110 kV1030
Site score48100

How the site score works in Germany · Search sites in North Rhine-Westphalia

Parcels in this site

Adjacent parcels that share at least 10 m of boundary, merged up to 50 ha, largest first. Each links to its cadastre record.