Power plant · Conwy, Wales, United Kingdom

Moel Maelogen A Phase 2

Moel Maelogen A Phase 2 is a power plant in Conwy, Wales, United Kingdom, with 11.7 MW of capacity, operated by John Laing Environmental Assets Group.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationConwy (coordinates), WalesDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressMoel Maelogen, Nr Llanrwst, Conwy, GwyneddDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusOperating (operational)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Start year2008DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Onshore or offshoreOnshoreDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date26 Nov 2004 (permit 0/27445, Town and Country Planning Act, issued by Conwy)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date12 Jun 2003 (reference 0/27445, planning authority Conwy)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date26 Nov 2004 (granted, reference 0/27445, planning authority Conwy)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorJohn Laing Environmental Assets GroupDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity11.7 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Units8 units (1.3 MW per unit)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologyWind OnshoreDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates53.1372, -3.7225DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Commissioned
  2. Permit granted (planning authority Conwy, reference 0/27445)
  3. Permit applied for (planning authority Conwy, reference 0/27445)

How it compares

Moel Maelogen A Phase 2 is the 127th-largest of 424 power plants in Wales and the 1,722nd-largest of 5,050 in the United Kingdom by capacity; its 11.7 MW is <0.1% of the 115,622 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.

WithinRankTotalShare
Wales127th of 4249,068 MW0.13%
United Kingdom1,722nd of 5,050115,622 MW<0.1%
All power plants in our data6,484th of 12,0321,190,447 MW<0.1%

Timeline

Dated facts about this power plant from its sources, oldest first.

  1. Started operating

Nearby

Within 50 km of this power plant: 1 transmission line, measured from the coordinates in the facts above.

NameKindSizeStatusDistance
North Wales Wind Farms ConnectionTransmission line—Permitted18 km

Operator and place

More from John Laing Environmental Assets Group

Other power plants in Wales

All 616 power plants in Wales, United Kingdom

Data on this page