Dyffryn Brodyn Wind Farm is a wind power plant in Carmarthenshire, Wales, United Kingdom, with 5.5 MW of capacity, operated by Renewable Energy Systems.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Carmarthenshire (coordinates), Wales | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Address | Dyffryn Brodyn Wind Farm, near Llanboidy, north of St Clears | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Status | Operating (operational) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Start year | 1994 | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Onshore or offshore | Onshore | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Permit date | 1 Jan 1994 (Town and Country Planning Act, issued by Carmarthenshire) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Decision date | 1 Jan 1994 (granted, planning authority Carmarthenshire) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Operator | Renewable Energy Systems (Renewable Energy Systems (RES)) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Capacity | 5.5 MW | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Units | 11 units (0.5 MW per unit) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Technology | Wind Onshore | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Coordinates | 51.9117, -4.5885 | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.
Request researchLatest events
Dated events about this power plant from official notices and registers, newest first. All recent changes.
- Commissioned
- Permit granted (planning authority Carmarthenshire)
How it compares
Dyffryn Brodyn Wind Farm is the 243rd-largest of 451 power plants in Wales and the 3,216th-largest of 5,834 in the United Kingdom by capacity; its 5.5 MW is <0.1% of the 200,500 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.
| Within | Rank | Total | Share |
|---|---|---|---|
| Wales | 243rd of 451 | 16,665 MW | <0.1% |
| United Kingdom | 3,216th of 5,834 | 200,500 MW | <0.1% |
| All power plants in our data | 11,798th of 15,799 | 1,918,113 MW | <0.1% |
Timeline
Dated facts about this power plant from its sources, oldest first.
- Started operating
Nearby
Within 50 km of this power plant: 1 transmission line, measured from the coordinates in the facts above.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Brechfa Forest Connection | Transmission line | — | Permitted | 27 km |
Operator and place
More from Renewable Energy Systems
- Clune Wind Farm - Wind Farm187 MW · planned
- Bloch Wind Farm & Battery Storage (Solway Bank Extension)126 MW · planned
- Longcroft Wind Farm125 MW · planned
- Clune Wind Farm - Battery Energy Storage100 MW · planned
- South Thinford Lane, Thinford - Energy Storage99.9 MW
- Llanbrynmair Wind Farm69 MW
- Cairn Duhie Wind Farm67.2 MW · permitted
- Keirs Hill (Sclenteuch) Wind Farm57.8 MW
Other power plants in Wales
- Pembroke2,325 MW
- Dinorwig1,728 MW
- Aberthaw B1,559 MW
- Connahs Quay1,380 MW
- Severn Power Ltd850 MW
- Gwynt y Mor576 MW
- Deeside498 MW
- Ffestiniog360 MW
Data on this page
- Contains public sector information licensed under the Open Government Licence v3.0. DUKES 5.11: Power stations in the United Kingdom, Open Government Licence v3.0.
- Contains public sector information licensed under the Open Government Licence v3.0. DESNZ Renewable Energy Planning Database (REPD), Open Government Licence v3.0.
- Source: U.S. Energy Information Administration (Sep 2026). EIA-860 / 860M / 923, Public domain.
- JRC Open Power Plants Database (JRC-PPDB-OPEN), European Commission, Joint Research Centre. JRC Open Power Plants Database (JRC-PPDB-OPEN), CC BY 4.0.
- Bundesnetzagentur, Marktstammdatenregister. Marktstammdatenregister, DL-DE-BY-2.0.
- Dutch power station owners' and operators' pages. Dutch power station owners' and operators' pages, Facts only, each linked to its page.
- Contains public sector information licensed under the Open Government Licence v3.0. Planning Inspectorate: National Infrastructure Projects, Open Government Licence v3.0.
- RVO SDE(+)(+) projecten in beheer and SDE viewer. RVO SDE(+)(+) projecten in beheer and SDE viewer, Free reuse, no attribution required.
- Wikidata. Wikidata, CC0 1.0.