Power plant · Highland, Scotland, United Kingdom

Gartymore Wind Farm

Gartymore Wind Farm is a cancelled power plant in Highland, Scotland, United Kingdom, with 10.5 MW of capacity, operated by Renewable Energy Systems.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationHighland (coordinates), ScotlandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressGartymore EstateDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusCancelled (planning permission refused)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Onshore or offshoreOnshoreDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date19 Oct 1995 (planning authority Highland)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date19 Jul 1999 (refused, planning authority Highland)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorRenewable Energy Systems (Renewable Energy Systems (RES))DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity10.5 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Units14 unitsDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologyWind OnshoreDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates58.1188, -3.7165DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Permit refused (planning authority Highland)
  2. Permit applied for (planning authority Highland)

How it compares

Gartymore Wind Farm is the 603rd-largest of 1,196 power plants in Scotland and the 1,803rd-largest of 5,050 in the United Kingdom by capacity; its 10.5 MW is <0.1% of the 115,622 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.

WithinRankTotalShare
Scotland603rd of 1,19634,589 MW<0.1%
United Kingdom1,803rd of 5,050115,622 MW<0.1%
All power plants in our data6,880th of 12,0321,190,447 MW<0.1%

Nearby

Within 50 km of this power plant: 34 grid connections (17 operating, 263 MW) and 24 substations, measured from the coordinates in the facts above. The table shows the nearest 6, up to 3 per kind.

NameKindSizeStatusDistance
Helmsdale PrimarySubstation——3.4 km
Crakaig Wind Energy Hub grid connectionGrid connection85.2 MWPlanned5.2 km
50MW grid connectionGrid connection52.7 MWPlanned14 km
Brora PrimarySubstation——14 km
Brora GSPSubstation——14 km
Boulfruich Windfarm grid connectionGrid connection14.3 MWOperating25 km

Operator and place

More from Renewable Energy Systems

Other power plants in Scotland

All 2093 power plants in Scotland, United Kingdom

Data on this page