Power plant · Angus, Scotland, United Kingdom

East Ballochy

East Ballochy is a permitted power plant in Angus, Scotland, United Kingdom, with 39.9 MW of capacity, operated by ScottishPower Renewables.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationAngus (coordinates), ScotlandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressField 400M SE Of East Ballochy, East Ballochy, Montrose, Tayside, DD10 9LPDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusPermitted (planning permission granted)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date15 Sept 2020 (permit 20/00019/FULM, Town and Country Planning Act, issued by Angus)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date27 Jan 2020 (ref. 20/00019/FULM, Angus)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date15 Sept 2020 (granted, ref. 20/00019/FULM, Angus)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorScottishPower RenewablesDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity39.9 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologySolar PhotovoltaicsDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Area162 ha (solar site area)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates56.7485, -2.5375DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Know more about this power plant, or want an introduction to its operator? Ask us.

How it compares

East Ballochy is the 462nd-largest of 872 power plants planned, permitted or under construction in Scotland and the 1,438th-largest of 3,222 in the United Kingdom by capacity; its 39.9 MW is <0.1% of the 300,661 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.

WithinRankTotalShare
Scotland462nd of 87299,272 MW<0.1%
United Kingdom1,438th of 3,222300,661 MW<0.1%
All power plants planned, permitted or under construction in our data2,654th of 6,455664,240 MW<0.1%

Nearby

Within 50 km of this power plant: 96 grid connections (28 operating, 361 MW) and 69 substations, measured from the coordinates in the facts above. The table shows the nearest 6, up to 3 per kind.

NameKindSizeStatusDistance
Craigo and Glenskinno Farm Solar grid connectionGrid connection75 MWPlanned1.2 km
Ballochy Solar Farm grid connectionGrid connection23.3 MWPlanned2.1 km
Logie Pert PrimarySubstation——2.5 km
Balwyllo Farm grid connectionGrid connection49.9 MWPlanned3.3 km
Bridge of Dun GSPSubstation——3.3 km
Bridge of Dun PrimarySubstation——3.3 km

Operator and place

More from ScottishPower Renewables

Other power plants in Scotland

All 2093 power plants in Scotland, United Kingdom