Power plant · Perth and Kinross, Scotland, United Kingdom

Coupar Angus Substation, Pleasance Road - Solar Farm

Coupar Angus Substation, Pleasance Road - Solar Farm is a cancelled power plant in Perth and Kinross, Scotland, United Kingdom, with 49.9 MW of capacity, operated by Coupar Two Limited.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationPerth and Kinross (coordinates), ScotlandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressSe/O Coupar Angus Substation, Pleasance Road, Coupar Angus, Blairgowrie, PH13 9AADESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusCancelled (planning permission refused)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date18 Aug 2023 (reference 23/01294/FLM, planning authority Perth and Kinross)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date14 Dec 2023 (refused, reference 23/01294/FLM, planning authority Perth and Kinross)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorCoupar Two LimitedDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity49.9 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologySolar PhotovoltaicsDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Area90.6 ha (solar site area)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates56.5365, -3.2643DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Permit refused (planning authority Perth and Kinross, reference 23/01294/FLM)
  2. Permit applied for (planning authority Perth and Kinross, reference 23/01294/FLM)

How it compares

Coupar Angus Substation, Pleasance Road - Solar Farm is the 161st-largest of 1,196 power plants in Scotland and the 362nd-largest of 5,050 in the United Kingdom by capacity; its 49.9 MW is <0.1% of the 115,622 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.

WithinRankTotalShare
Scotland161st of 1,19634,589 MW0.14%
United Kingdom362nd of 5,050115,622 MW<0.1%
All power plants in our data1,865th of 12,0321,190,447 MW<0.1%

Nearby

Within 50 km of this power plant: 100 grid connections (30 operating, 406 MW) and 71 substations, measured from the coordinates in the facts above. The table shows the nearest 6, up to 3 per kind.

NameKindSizeStatusDistance
Abroath BESS (MSID 8771) EXP grid connectionGrid connection33.3 MWOperating0.5 km
Coupar Angus Battery Stor grid connectionGrid connection38 MWOperating0.5 km
Coupar Angus GSPSubstation——0.6 km
Coupar Angus PrimarySubstation——0.6 km
49.9MW BESS grid connectionGrid connection49.9 MWPlanned1.6 km
Blairgowrie PrimarySubstation——6.6 km

Operator and place

Other power plants in Scotland

All 2093 power plants in Scotland, United Kingdom