Power plant · Highland, Scotland, United Kingdom

Coille Linne Wind Farm- Wind Turbines

Coille Linne Wind Farm- Wind Turbines is a planned power plant in Highland, Scotland, United Kingdom, with 109 MW of capacity, operated by Energiekontor Limited.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationHighland (coordinates), ScotlandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Address21.9km Nw/o Lairg, 16km Se/o Altnaharra, Lairg, IV27 4BJDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusPlanned (planning application submitted)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Onshore or offshoreOnshoreDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date18 Jun 2025 (ref. ECU00005163, Scottish Government (S36))DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorEnergiekontor LimitedDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity109 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Units15 unitsDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologyWind OnshoreDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates58.0257, -4.3964DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Know more about this power plant, or want an introduction to its operator? Ask us.

How it compares

Coille Linne Wind Farm- Wind Turbines is the 131st-largest of 872 power plants planned, permitted or under construction in Scotland and the 409th-largest of 3,222 in the United Kingdom by capacity; its 109 MW is <0.1% of the 300,661 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.

WithinRankTotalShare
Scotland131st of 87299,272 MW0.11%
United Kingdom409th of 3,222300,661 MW<0.1%
All power plants planned, permitted or under construction in our data1,228th of 6,455664,240 MW<0.1%

Nearby

Within 50 km of this power plant: 36 grid connections (21 operating, 251 MW) and 31 substations, measured from the coordinates in the facts above. The table shows the nearest 6, up to 3 per kind.

NameKindSizeStatusDistance
Lairg GSPSubstation——0.6 km
Lairg PrimarySubstation——0.6 km
Lairg Power Station grid connectionGrid connection3.52 MWOperating0.6 km
DG - Lairg GSP grid connectionGrid connection52.7 MWPlanned0.7 km
CNOC na-Inghinn Wind grid connectionGrid connection4.75 MWOperating1.9 km
Conon Falls PrimarySubstation——9.2 km

Operator and place

More from Energiekontor Limited

Other power plants in Scotland

All 2093 power plants in Scotland, United Kingdom