Beinn an Tuirc Windfarm Phase 3 is a power plant under construction in Argyll and Bute, Scotland, United Kingdom, with 49.9 MW of capacity, operated by Scottish Power Renewables.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Argyll and Bute (coordinates), Scotland | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Address | Beinn An Tuirc Windfarm, Land At Meall Buidhe And South, A Chruach West Of Saddell Kin, Campbeltown, Strathclyde, Scotland, PA28 | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Status | Under construction | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Onshore or offshore | Onshore | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Permit date | 23 Feb 2017 (permit 15/03057/PP, Town and Country Planning Act, issued by Argyll and Bute) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Application date | 3 Nov 2015 (reference 15/03057/PP, planning authority Argyll and Bute) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Decision date | 23 Feb 2017 (granted, reference 15/03057/PP, planning authority Argyll and Bute) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Operator | Scottish Power Renewables | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Capacity | 49.9 MW | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Units | 19 units (2 MW per unit) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Technology | Wind Onshore | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Coordinates | 55.5471, -5.6093 | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.
Request researchLatest events
Dated events about this power plant from official notices and registers, newest first. All recent changes.
- Construction started
- Permit granted (planning authority Argyll and Bute, reference 15/03057/PP)
- Permit applied for (planning authority Argyll and Bute, reference 15/03057/PP)
How it compares
Beinn an Tuirc Windfarm Phase 3 is the 320th-largest of 872 power plants planned, permitted or under construction in Scotland and the 886th-largest of 3,222 in the United Kingdom by capacity; its 49.9 MW is <0.1% of the 300,461 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.
| Within | Rank | Total | Share |
|---|---|---|---|
| Scotland | 320th of 872 | 99,272 MW | <0.1% |
| United Kingdom | 886th of 3,222 | 300,461 MW | <0.1% |
| All power plants planned, permitted or under construction in our data | 1,966th of 6,455 | 664,040 MW | <0.1% |
Nearby
Within 50 km of this power plant: 25 grid connections (14 operating, 120 MW) and 21 substations, measured from the coordinates in the facts above. The table shows the nearest 6, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Allt Domhain Wind Farm grid connection | Grid connection | 64.8 MW | Planned | 4.7 km |
| Blary Hill Wind Generating Facility grid connection | Grid connection | 33.3 MW | Operating | 4.7 km |
| Auchadaduie Wind grid connection | Grid connection | 6.56 MW | Operating | 4.7 km |
| Carradale 1 GSP | Substation | — | — | 8.2 km |
| Carradale 2 GSP | Substation | — | — | 8.3 km |
| Dippen Primary | Substation | — | — | 8.4 km |
Operator and place
More from Scottish Power Renewables
- Ossian3,600 MW · permitted
- Machair2,000 MW · planned
- East Anglia 3 (EA 3)1,400 MW · under construction
- East Anglia 2 (EA 2)900 MW · permitted
- East Anglia 1 North (EA 4)800 MW · permitted
- East Anglia 1 (EA 1)714 MW
- Kilgallioch wind farm239 MW
- Harestanes136 MW
Other power plants in Scotland
- Seagreen1,075 MW
- Moray East950 MW
- Moray West Offshore Wind Farm Project882 MW
- Lewis Wind Farm (Barvas Moor)652 MW
- Beatrice588 MW
- Neart na Gaoithe450 MW
- Viking Wind Farm443 MW
- Cruachan440 MW
Data on this page
- Contains public sector information licensed under the Open Government Licence v3.0. DESNZ Renewable Energy Planning Database (REPD), Open Government Licence v3.0.
- Source: U.S. Energy Information Administration (Sep 2026). EIA-860 / 860M / 923, Public domain.
- Bundesnetzagentur, Marktstammdatenregister. Marktstammdatenregister, DL-DE-BY-2.0.
- Contains public sector information licensed under the Open Government Licence v3.0. Planning Inspectorate: National Infrastructure Projects, Open Government Licence v3.0.
- RVO SDE(+)(+) projecten in beheer and SDE viewer. RVO SDE(+)(+) projecten in beheer and SDE viewer, Free reuse, no attribution required.
- SSEN Distribution. SSEN Distribution data portal, CC BY 4.0.