Power plant · Highland, Scotland, United Kingdom

Balnespick Wind Farm

Balnespick Wind Farm is a planned power plant in Highland, Scotland, United Kingdom, with 55.8 MW of capacity, operated by Fred Olsen Renewables.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationHighland (coordinates), ScotlandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Address5 km east of Tomatin, 6 km north-west of CarrbridgeDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusPlanned (planning application submitted)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Onshore or offshoreOnshoreDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date20 Feb 2025 (reference ECU00004904, planning authority Scottish Government (S36))DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorFred Olsen RenewablesDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity55.8 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Units9 units (6.2 MW per unit)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologyWind OnshoreDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates57.3466, -3.8824DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

How it compares

Balnespick Wind Farm is the 273rd-largest of 872 power plants planned, permitted or under construction in Scotland and the 736th-largest of 3,222 in the United Kingdom by capacity; its 55.8 MW is <0.1% of the 300,661 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.

WithinRankTotalShare
Scotland273rd of 87299,272 MW<0.1%
United Kingdom736th of 3,222300,661 MW<0.1%
All power plants planned, permitted or under construction in our data1,768th of 6,455664,240 MW<0.1%

Nearby

Within 50 km of this power plant: 59 substations and 44 grid connections (20 operating, 473 MW), measured from the coordinates in the facts above. The table shows the nearest 6, up to 3 per kind.

NameKindSizeStatusDistance
Tomatin PrimarySubstation——7.7 km
TOM NAN Clach Farm Wind grid connectionGrid connection37.1 MWOperating13 km
Boat of Garten PrimarySubstation——14 km
Boat of Garten GSPSubstation——14 km
Boat of Garten BESS grid connectionGrid connection49.9 MWOperating14 km
Cairn Duhie Wind Farm grid connectionGrid connection104 MWPlanned19 km

Operator and place

More from Fred Olsen Renewables

Other power plants in Scotland

All 2093 power plants in Scotland, United Kingdom