Power plant · Herefordshire, County of, England, United Kingdom
Reeves Hill
Reeves Hill is a cancelled power plant in Herefordshire, County of, England, United Kingdom, with 9.2 MW of capacity, operated by Bolsterstone Innovative Energy.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Herefordshire, County of (coordinates), England | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Address | Reeves Hill, Reeves Lane, near Knighton, Shropshire | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Status | Cancelled (planning permission expired) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Onshore or offshore | Onshore | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Permit date | 26 Apr 2016 (permit NW081479/F, Town and Country Planning Act, issued by Herefordshire, County of) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Permit date | 14 Sept 2011 (permit NW081479/F, Town and Country Planning Act, issued by Herefordshire, County of) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Application date | 19 May 2008 (reference NW081479/F, planning authority Herefordshire, County of) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Decision date | 26 Apr 2016 (appeal granted, reference NW081479/F, planning authority Herefordshire, County of) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Decision date | 14 Sept 2011 (granted, reference NW081479/F, planning authority Herefordshire, County of) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Operator | Bolsterstone Innovative Energy | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Capacity | 9.2 MW | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Units | 4 units (2.3 MW per unit) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Technology | Wind Onshore | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Coordinates | 52.3202, -2.9973 | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
Know more about this power plant, or want an introduction to its operator? Ask us.
How it compares
Reeves Hill is the 1,232nd-largest of 3,430 power plants in England and the 2,023rd-largest of 5,050 in the United Kingdom by capacity; its 9.2 MW is <0.1% of the 115,642 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.
| Within | Rank | Total | Share |
|---|---|---|---|
| England | 1,232nd of 3,430 | 71,985 MW | <0.1% |
| United Kingdom | 2,023rd of 5,050 | 115,642 MW | <0.1% |
| All power plants in our data | 7,380th of 12,008 | 1,173,302 MW | <0.1% |
Timeline
Dated facts about this power plant from its sources, oldest first.
- Permit issued (Town and Country Planning Act), no. NW081479/F
- Permit issued (Town and Country Planning Act), no. NW081479/F
Nearby
Within 50 km of this power plant: 54 grid connections and 3 transmission lines, measured from the coordinates in the facts above. The table shows the nearest 6, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Heartsease grid connection | Grid connection | — | — | 3.7 km |
| Land at Stokesay grid connection | Grid connection | — | — | 18 km |
| Land OFF Park Lane Woofferton grid connection | Grid connection | — | — | 19 km |
| Mid Wales Electricity Connection (N Grid) | Transmission line | — | Cancelled | 43 km |
| SP Mid Wales (Electricity) Connections Project (SP Manweb) | Transmission line | — | Planned | 45 km |
| Green Gen Vyrnwy Frankton | Transmission line | — | Planned | 49 km |
Operator and place
Other power plants in England
- Walpole Flexible Generation Project2,000 MW
- Outer Dowsing Offshore Wind Farm1,500 MW
- Hornsea 2 - Optimus and Breesea1,320 MW
- Hornsea 1 - Heron & Njord1,218 MW
- Atlantic Array One - Bristol Channel Zone1,200 MW
- Five Estuaries - Wind Farm1,080 MW
- Rugeley Power Plant Conversion1,000 MW
- Teesworks Battery Storage Project1,000 MW
Data on this page
- DESNZ Renewable Energy Planning Database (REPD). DESNZ Renewable Energy Planning Database (REPD), Open Government Licence v3.0.
- Source: U.S. Energy Information Administration (Sep 2026). EIA-860 / 860M / 923, Public domain.
- Bundesnetzagentur, Marktstammdatenregister. Marktstammdatenregister, DL-DE-BY-2.0.
- NGED Connected Data portal. NGED Connected Data portal, Terms not verified.
- Planning Inspectorate: National Infrastructure Projects. Planning Inspectorate: National Infrastructure Projects, Open Government Licence v3.0.
- RVO SDE(+)(+) projecten in beheer and SDE viewer. RVO SDE(+)(+) projecten in beheer and SDE viewer, Free reuse, no attribution required.