Power plant · Forest of Dean, England, United Kingdom
Plusterwine House - Anaerobic Digestion Plant (Retrospective)
Plusterwine House - Anaerobic Digestion Plant (Retrospective) is a power plant in Forest of Dean, England, United Kingdom, with 1.5 MW of capacity, operated by Plusterwine Biogas Limited.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Forest of Dean (coordinates), England | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Address | Plusterwine Biogas Limited, Plusterwine House Station Road, GL15 6PN | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Status | Operating (operational) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Start year | 2016 | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Permit date | 2 Mar 2021 (permit P1764/20/FUL, Town and Country Planning Act, issued by Forest of Dean) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Application date | 26 Oct 2020 (reference P1764/20/FUL, planning authority Forest of Dean) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Decision date | 2 Mar 2021 (granted, reference P1764/20/FUL, planning authority Forest of Dean) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Operator | Plusterwine Biogas Limited | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Capacity | 1.5 MW | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Technology | Anaerobic Digestion | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Coordinates | 51.6913, -2.5850 | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.
Request researchHow it compares
Plusterwine House - Anaerobic Digestion Plant (Retrospective) is the 3,048th-largest of 3,430 power plants in England and the 4,531st-largest of 5,050 in the United Kingdom by capacity; its 1.5 MW is <0.1% of the 115,642 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.
| Within | Rank | Total | Share |
|---|---|---|---|
| England | 3,048th of 3,430 | 71,985 MW | <0.1% |
| United Kingdom | 4,531st of 5,050 | 115,642 MW | <0.1% |
| All power plants in our data | 11,060th of 12,008 | 1,173,302 MW | <0.1% |
Timeline
Dated facts about this power plant from its sources, oldest first.
- Started operating
- Permit issued (Town and Country Planning Act), no. P1764/20/FUL
Nearby
Within 50 km of this power plant: 60 grid connections (34 operating, 625 MW), 26 substations, 10 data centers, 2 transmission lines and 1 AI supercomputer, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| nLighten Bristol | Data center | — | — | 17 km |
| DXC Technology | Data center | — | — | 21 km |
| University of Bristol Isambard-AI | AI supercomputer | 5,448 H100e | Operating | 23 km |
| Alderton Primary | Substation | — | — | 29 km |
| Tetbury Primary | Substation | — | — | 31 km |
| Castle Combe PV grid connection | Grid connection | 11.4 MW | Operating | 34 km |
| Marsh Farm B PV grid connection | Grid connection | 11.4 MW | Operating | 34 km |
| Hullavington PV Farm grid connection | Grid connection | 6.65 MW | Operating | 34 km |
| Vantage Data Centers - CWL13 | Data center | — | — | 34 km |
Operator and place
Other power plants in England
- Walpole Flexible Generation Project2,000 MW
- Outer Dowsing Offshore Wind Farm1,500 MW
- Hornsea 2 - Optimus and Breesea1,320 MW
- Hornsea 1 - Heron & Njord1,218 MW
- Atlantic Array One - Bristol Channel Zone1,200 MW
- Five Estuaries - Wind Farm1,080 MW
- Rugeley Power Plant Conversion1,000 MW
- Teesworks Battery Storage Project1,000 MW
Data on this page
- DESNZ Renewable Energy Planning Database (REPD). DESNZ Renewable Energy Planning Database (REPD), Open Government Licence v3.0.
- Source: U.S. Energy Information Administration (Sep 2026). EIA-860 / 860M / 923, Public domain.
- Epoch AI. Epoch AI supercomputers, CC BY 4.0.
- Bundesnetzagentur, Marktstammdatenregister. Marktstammdatenregister, DL-DE-BY-2.0.
- © OpenStreetMap contributors. OpenStreetMap data centers, ODbL 1.0.
- Planning Inspectorate: National Infrastructure Projects. Planning Inspectorate: National Infrastructure Projects, Open Government Licence v3.0.