Power plant · Tendring, England, United Kingdom

Burnt Ash Farm

Burnt Ash Farm is a cancelled power plant in Tendring, England, United Kingdom, with 13.5 MW of capacity, operated by Kinetica Solar.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationTendring (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressBurnt Ash Farm Spinnels Lane Wix Manningtree Essex, CO11 2UJDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusCancelled (appeal refused)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date17 Dec 2013 (reference 13/01340/FUL, planning authority Tendring)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date8 Sept 2015 (appeal refused, reference 13/01340/FUL, planning authority Tendring)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date1 Aug 2014 (refused, reference 13/01340/FUL, planning authority Tendring)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorKinetica SolarDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity13.5 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologySolar PhotovoltaicsDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Area25.7 ha (solar site area)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates51.9217, 1.1504DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Permit refused (appeal refused, planning authority Tendring, reference 13/01340/FUL)
  2. Permit refused (planning authority Tendring, reference 13/01340/FUL)
  3. Permit applied for (planning authority Tendring, reference 13/01340/FUL)

How it compares

Burnt Ash Farm is the 867th-largest of 3,430 power plants in England and the 1,539th-largest of 5,050 in the United Kingdom by capacity; its 13.5 MW is <0.1% of the 115,622 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.

WithinRankTotalShare
England867th of 3,43071,965 MW<0.1%
United Kingdom1,539th of 5,050115,622 MW<0.1%
All power plants in our data5,673rd of 12,0321,190,447 MW<0.1%

Nearby

Within 50 km of this power plant: 3 transmission lines, measured from the coordinates in the facts above.

NameKindSizeStatusDistance
Bramford to TwinsteadTransmission line—Permitted22 km
LionLink InterconnectorTransmission line—Planned40 km
Sea LinkTransmission line—Planned45 km

Operator and place

More from Kinetica Solar

Other power plants in England

All 5809 power plants in England, United Kingdom

Data on this page