Power plant · South Hams, England, United Kingdom

Balls Wood Solar Farm

Balls Wood Solar Farm is a power plant in South Hams, England, United Kingdom, with 8.7 MW of capacity, operated by Due South Energy & SunE Project6 Ltd.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationSouth Hams (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressBalls Wood, Plymouth, DevonDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusOperating (operational)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Start year2015DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date14 Oct 2014 (permit 07/1814/14/F, Town and Country Planning Act, issued by South Hams)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date15 Jul 2014 (reference 07/1814/14/F, planning authority South Hams)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date14 Oct 2014 (granted, reference 07/1814/14/F, planning authority South Hams)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorDue South Energy & SunE Project6 LtdDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity8.7 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologySolar PhotovoltaicsDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates50.3499, -4.0347DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Know more about this power plant, or want an introduction to its operator? Ask us.

How it compares

Balls Wood Solar Farm is the 1,299th-largest of 3,430 power plants in England and the 2,115th-largest of 5,050 in the United Kingdom by capacity; its 8.7 MW is <0.1% of the 115,642 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.

WithinRankTotalShare
England1,299th of 3,43071,985 MW<0.1%
United Kingdom2,115th of 5,050115,642 MW<0.1%
All power plants in our data7,508th of 12,0081,173,302 MW<0.1%

Timeline

Dated facts about this power plant from its sources, oldest first.

  1. Permit issued (Town and Country Planning Act), no. 07/1814/14/F
  2. Started operating

Nearby

Within 50 km of this power plant: 107 grid connections and 1 mine, measured from the coordinates in the facts above. The table shows the nearest 4, up to 3 per kind.

NameKindSizeStatusDistance
Steer Point, Brixton, Devon grid connectionGrid connection——1.8 km
Newton Downs Farm Newton Downs, Newton Ferrers grid connectionGrid connection——2.3 km
Tuxton Farm grid connectionGrid connection——2.8 km
Tungsten WestMine——7.3 km

Operator and place

Other power plants in England

All 5809 power plants in England, United Kingdom