Owner · Company

Viridis Energy (Norgen) Limited

Viridis Energy (Norgen) Limited holds 7 grid connections in the United Kingdom, with 13.7 MW of capacity between them.

Portfolio

The 7 assets and rights linked to Viridis Energy (Norgen) Limited, by class, with its role in each.

Grid connections 7 · 13.7 MW

Grid connectionLocationRoleCapacity
Clitheroe Works grid connectionEngland, United KingdomHolder6.12 MW
Landfill gas 1.9 MW grid connection at LunanheadScotland, United KingdomHolder1.9 MW
Hespin Wood Landfill grid connectionEngland, United KingdomHolder1.33 MW
Salt Ayre Landfill 3 grid connectionEngland, United KingdomHolder1.15 MW
Salt Ayre Landfill grid connectionEngland, United KingdomHolder1.15 MW
Landfill gas 1.093 MW grid connection at Corfe MullenEngland, United KingdomHolder1.09 MW
Salt Ayre Landfill 2 grid connectionEngland, United KingdomHolder1 MW

By country

Where the assets and rights are.

Partners and counterparties

Owners, operators and grid operators on the same assets.

Facts

FactValueSource
Name in the sourceVIRIDIS ENERGY (NORGEN) LIMITEDSP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026

Own or advise on any of these assets, or looking to buy? Tell us; introductions are private.