Owner · Company
Conergy West Sussex
Conergy West Sussex operates 2 power plants in the United Kingdom.
Portfolio
The 2 assets and rights Conergy West Sussex owns, operates or holds, by class, with its role in each. Sizes are the whole asset's, so they are not added up: the sources give no share for this owner.
Power plants 2
| Power plant | Location | Role | Capacity |
|---|---|---|---|
| Biglis Farm | Vale of Glamorgan, Wales, United Kingdom | Operator | 5 MW |
| Land At Guston Court Farm | Dover, England, United Kingdom | Operator | 5 MW |
By country
Where the assets and rights are.
- The United Kingdom2 power plants
Latest events
Dated events about Conergy West Sussex and its assets from official notices and registers, newest first. All recent changes.
- Commissioned: Biglis Farm
- Commissioned: Land At Guston Court Farm
- Permit granted: Biglis Farm (planning authority Vale of Glamorgan, reference 2015/00573/FUL)
- Permit applied for: Biglis Farm (planning authority Vale of Glamorgan, reference 2015/00573/FUL)
- Permit granted: Land At Guston Court Farm (planning authority Dover, reference 14/01133)
- Permit applied for: Land At Guston Court Farm (planning authority Dover, reference 14/01133)
Research on Conergy West Sussex.Its full portfolio, its parent companies, and an introduction to the people who decide on buying and selling.
Request researchData on this page
- Contains public sector information licensed under the Open Government Licence v3.0. DESNZ Renewable Energy Planning Database (REPD), Open Government Licence v3.0.