Grid connection · Loudoun County, Virginia, United States
Hamilton 230 kV grid connection (PJM C01-1882)
Hamilton 230 kV grid connection (PJM C01-1882) is a planned grid connection in Loudoun County, Virginia, United States, with 500 MW of capacity, held by Cedar Holdco LLC.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Loudoun County (connects at Hamilton 230 kV) | PJM New Services Queue · Free reuse · checked 24 Oct 2026 |
| Status | Planned (active, cluster C01 Phase 1) | PJM New Services Queue · Free reuse · checked 24 Oct 2026 |
| Holder | Cedar Holdco LLC | PJM New Services Queue · Free reuse · checked 24 Oct 2026 |
| Capacity | 500 MW | PJM New Services Queue · Free reuse · checked 24 Oct 2026 |
| Technology | Storage | PJM New Services Queue · Free reuse · checked 24 Oct 2026 |
| Grid operator | PJM Interconnection, L.L.C. | PJM New Services Queue · Free reuse · checked 24 Oct 2026 |
| Queue date | 27 Apr 2026 | PJM New Services Queue · Free reuse · checked 24 Oct 2026 |
| Connection date | 31 Oct 2030 (proposed) | PJM New Services Queue · Free reuse · checked 24 Oct 2026 |
Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.
Request researchLatest events
Dated events about this grid connection from official notices and registers, newest first. All recent changes.
- Entered the connection queue
How it compares
Hamilton 230 kV grid connection (PJM C01-1882) is the 24th-largest of 415 grid connections in Virginia and the 349th-largest of 4,021 in the United States by capacity; its 500 MW is <0.1% of the 923,876 MW we hold for the United States. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.
| Within | Rank | Total | Share |
|---|---|---|---|
| Virginia | 24th of 415 | 62,531 MW | 0.8% |
| United States | 349th of 4,021 | 923,876 MW | <0.1% |
| All grid connections in our data | 650th of 7,928 | 1,372,494 MW | <0.1% |
Timeline
Dated facts about this grid connection from its sources, oldest first.
- Due to connect
Holder, grid operator and place
More from Cedar Holdco LLC
- Bristers 500 kV grid connection (PJM C01-1884)1,000 MW
- Ohio Central 345 kV grid connection (PJM C01-1886)1,000 MW
- East Flemington 230 kV grid connection (PJM C01-1875)500 MW
- Dickerson - Quince Orchard 230 kV grid connection (PJM C01-1885)500 MW
- Wythe 138 kV grid connection (PJM C01-1879)300 MW
- Strasburg 138 kV grid connection (PJM C01-1876)250 MW
- Carrollton 138 kV grid connection (PJM C01-1878)250 MW
Other grid connections in Virginia
- Joshua Falls 765 kV grid connection (PJM C01-1390)2,300 MW
- Cunningham - Elmont 500 kV grid connection (PJM C01-1111)1,694 MW
- Cunningham - Elmont 500 kV grid connection (PJM C01-1112)1,694 MW
- Bristers 500 kV grid connection (PJM C01-1884)1,000 MW
- CVOW 2, OSS 2 – T2G07 grid connection (PJM AF1-124 - moved to TC1)836 MW
- CVOW 2, OSS 2 – T2G07 grid connection (PJM AF1-124)836 MW
- CVOW 1, OSS 1 - T1L11 grid connection (PJM AF1-123 - moved to TC1)833 MW
- CVOW 1, OSS 1 - T1L11 grid connection (PJM AF1-123)833 MW
Data on this page
- California ISO. CAISO queue report, CAISO Privacy and Terms of Use.
- SP Electricity North West, via Northern Powergrid Open Data. SP Electricity North West open data portal, CC BY 4.0.
- ERCOT GIS report. ERCOT GIS report, ERCOT Terms of Use.
- Supported by National Energy SO Open Data. NESO TEC Register, NESO Open Data Licence v1.0.
- Supported by Northern Powergrid Open Data. Northern Powergrid open data portal, Northern Powergrid Open Data Licence v1.0.
- NYISO interconnection queue. NYISO interconnection queue, Free reuse.
- PJM New Services Queue. PJM New Services Queue, Free reuse.
- SP Energy Networks, via Northern Powergrid Open Data. SP Energy Networks open data portal, CC BY 4.0.
- SSEN Distribution. SSEN Distribution data portal, CC BY 4.0.