Vanceville 138 kV grid connection (PJM C01-1174)

Vanceville 138 kV grid connection (PJM C01-1174) is a planned grid connection in Washington County, Pennsylvania, United States, with 200 MW of capacity, held by Idemitsu Renewables America Development LLC.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationWashington County (connects at Vanceville 138 kV)PJM New Services Queue · Free reuse · checked 24 Oct 2026
StatusPlanned (active, cluster C01 Phase 1)PJM New Services Queue · Free reuse · checked 24 Oct 2026
HolderIdemitsu Renewables America Development LLCPJM New Services Queue · Free reuse · checked 24 Oct 2026
Capacity200 MWPJM New Services Queue · Free reuse · checked 24 Oct 2026
TechnologyStorage (registered as Storage)PJM New Services Queue · Free reuse · checked 24 Oct 2026
Grid operatorPJM Interconnection, L.L.C.PJM New Services Queue · Free reuse · checked 24 Oct 2026
Queue date25 Apr 2026PJM New Services Queue · Free reuse · checked 24 Oct 2026
Connection date31 Dec 2030 (proposed)PJM New Services Queue · Free reuse · checked 24 Oct 2026

Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.

Request research

How it compares

Vanceville 138 kV grid connection (PJM C01-1174) is the 50th-largest of 204 grid connections in Pennsylvania and the 1,457th-largest of 3,711 in the United States by capacity; its 200 MW is <0.1% of the 833,233 MW we hold for the United States. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
Pennsylvania50th of 20446,972 MW0.43%
United States1,457th of 3,711833,233 MW<0.1%
All grid connections in our data1,776th of 7,6161,281,251 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Entered the connection queue
  2. Due to connect

Holder, grid operator and place

More from Idemitsu Renewables America Development LLC

Other grid connections in Pennsylvania

All 204 grid connections in Pennsylvania, United States

Data on this page