Grid connection · Berrien County, Michigan, United States
Olive - Cook 345 kV grid connection (PJM C01-2196)
Olive - Cook 345 kV grid connection (PJM C01-2196) is a planned grid connection in Berrien County, Michigan, United States, with 135 MW of capacity, held by Railway Wind, LLC.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Berrien County (connects at Olive - Cook 345 kV) | PJM New Services Queue · Free reuse · checked 24 Oct 2026 |
| Status | Planned (active, cluster C01 Phase 1) | PJM New Services Queue · Free reuse · checked 24 Oct 2026 |
| Holder | Railway Wind, LLC | PJM New Services Queue · Free reuse · checked 24 Oct 2026 |
| Capacity | 135 MW | PJM New Services Queue · Free reuse · checked 24 Oct 2026 |
| Technology | Wind (registered as Wind) | PJM New Services Queue · Free reuse · checked 24 Oct 2026 |
| Grid operator | PJM Interconnection, L.L.C. | PJM New Services Queue · Free reuse · checked 24 Oct 2026 |
| Queue date | 27 Apr 2026 | PJM New Services Queue · Free reuse · checked 24 Oct 2026 |
| Connection date | 31 Dec 2031 (proposed) | PJM New Services Queue · Free reuse · checked 24 Oct 2026 |
Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.
Request researchHow it compares
Olive - Cook 345 kV grid connection (PJM C01-2196) is the 12th-largest of 22 grid connections in Michigan and the 2,081st-largest of 3,711 in the United States by capacity; its 135 MW is <0.1% of the 833,233 MW we hold for the United States. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.
| Within | Rank | Total | Share |
|---|---|---|---|
| Michigan | 12th of 22 | 3,074 MW | 4.4% |
| United States | 2,081st of 3,711 | 833,233 MW | <0.1% |
| All grid connections in our data | 2,441st of 7,616 | 1,281,251 MW | <0.1% |
Timeline
Dated facts about this grid connection from its sources, oldest first.
- Entered the connection queue
- Due to connect
Holder, grid operator and place
More from Railway Wind, LLC
Other grid connections in Michigan
- Olive - Cook 345 kV grid connection (PJM C01-2194)300 MW
- Three Lakes Solar grid connection (PJM AF1-176 - moved to TC1)300 MW
- Three Lakes Solar grid connection (PJM AF1-176)300 MW
- Cass County Solar grid connection (PJM AF2-396 - moved to TC1)200 MW
- Cass County Solar grid connection (PJM AF2-396)200 MW
- Sodus 138 kV grid connection (PJM C01-1350)200 MW
- Twin Branch - Argenta 345 kV grid connection (PJM C01-1203)200 MW
- Twin Branch - Argenta 345 kV grid connection (PJM C01-1409)200 MW
Data on this page
- California ISO. Checked 2026-10-24. CAISO queue report, CAISO Privacy and Terms of Use.
- SP Electricity North West, via Northern Powergrid Open Data. SP Electricity North West open data portal, CC BY 4.0.
- ERCOT GIS report. ERCOT GIS report, ERCOT Terms of Use.
- Supported by National Energy SO Open Data. NESO TEC Register, NESO Open Data Licence v1.0.
- Supported by Northern Powergrid Open Data. Northern Powergrid open data portal, Northern Powergrid Open Data Licence v1.0.
- NYISO interconnection queue. NYISO interconnection queue, Free reuse.
- PJM New Services Queue. PJM New Services Queue, Free reuse.
- SP Energy Networks, via Northern Powergrid Open Data. SP Energy Networks open data portal, CC BY 4.0.
- SSEN Distribution. SSEN Distribution data portal, CC BY 4.0.