Grid connection · Yuma County, Arizona, United States

Ironwood Solar grid connection (CAISO 1435)

Ironwood Solar grid connection (CAISO 1435) is a planned grid connection in Yuma County, Arizona, United States, with 250 MW of capacity, connected by California Independent System Operator Corporation.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
Name in the sourceIRONWOOD SOLAR grid connection (CAISO 1435)CAISO queue report · CAISO Privacy and Terms of Use · checked 24 Oct 2026
LocationYuma County (connects at Hoodoo Wash Switchyard 500 kV)CAISO queue report · CAISO Privacy and Terms of Use · checked 24 Oct 2026
StatusPlanned (active; interconnection agreement executed, cluster C10)CAISO queue report · CAISO Privacy and Terms of Use · checked 24 Oct 2026
Capacity250 MWCAISO queue report · CAISO Privacy and Terms of Use · checked 24 Oct 2026
TechnologyStorage (registered as Photovoltaic Solar / Storage Battery)CAISO queue report · CAISO Privacy and Terms of Use · checked 24 Oct 2026
TechnologySolar (registered as Photovoltaic Solar / Storage Battery)CAISO queue report · CAISO Privacy and Terms of Use · checked 24 Oct 2026
Grid operatorCalifornia Independent System Operator CorporationCAISO queue report · CAISO Privacy and Terms of Use · checked 24 Oct 2026
Queue date1 May 2017CAISO queue report · CAISO Privacy and Terms of Use · checked 24 Oct 2026
Connection date30 Jun 2030 (proposed)CAISO queue report · CAISO Privacy and Terms of Use · checked 24 Oct 2026

Research on this grid connection and its grid operator.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the grid operator.

Request research

Latest events

Dated events about this grid connection from official notices and registers, newest first. All recent changes.

  1. Entered the connection queue

How it compares

Ironwood Solar grid connection (CAISO 1435) is the 18th-largest of 26 grid connections in Arizona and the 1,123rd-largest of 4,021 in the United States by capacity; its 250 MW is <0.1% of the 923,876 MW we hold for the United States. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
Arizona18th of 2613,740 MW1.8%
United States1,123rd of 4,021923,876 MW<0.1%
All grid connections in our data1,434th of 7,9281,372,494 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Due to connect

Grid operator and place

More from California Independent System Operator Corporation

Other grid connections in Arizona

All 26 grid connections in Arizona, United States

Data on this page