Grid connection · Maricopa County, Arizona, United States

Baler 1 grid connection (CAISO 55299)

Baler 1 grid connection (CAISO 55299) is a planned grid connection in Maricopa County, Arizona, United States, with 920 MW of capacity, connected by California Independent System Operator Corporation.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationMaricopa County (connects at Hoodoo Wash - Hassayampa (SDGE Portion Only)), Yuma County (connects at Hoodoo Wash - Hassayampa (SDGE Portion Only))CAISO queue report · CAISO Privacy and Terms of Use · checked 24 Oct 2026
StatusPlanned (cluster C16)CAISO queue report · CAISO Privacy and Terms of Use · checked 24 Oct 2026
Capacity920 MWCAISO queue report · CAISO Privacy and Terms of Use · checked 24 Oct 2026
TechnologyStorage (registered as Photovoltaic/Solar, Storage/Battery)CAISO queue report · CAISO Privacy and Terms of Use · checked 24 Oct 2026
TechnologySolar (registered as Photovoltaic/Solar, Storage/Battery)CAISO queue report · CAISO Privacy and Terms of Use · checked 24 Oct 2026
Grid operatorCalifornia Independent System Operator CorporationCAISO queue report · CAISO Privacy and Terms of Use · checked 24 Oct 2026
Queue date1 Oct 2026CAISO queue report · CAISO Privacy and Terms of Use · checked 24 Oct 2026
Connection date5 Oct 2033 (proposed)CAISO queue report · CAISO Privacy and Terms of Use · checked 24 Oct 2026

Research on this grid connection and its grid operator.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the grid operator.

Request research

Latest events

Dated events about this grid connection from official notices and registers, newest first. All recent changes.

  1. Entered the connection queue

How it compares

Baler 1 grid connection (CAISO 55299) is the 5th-largest of 26 grid connections in Arizona and the 140th-largest of 4,021 in the United States by capacity; its 920 MW is <0.1% of the 923,876 MW we hold for the United States. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
Arizona5th of 2613,740 MW6.7%
United States140th of 4,021923,876 MW<0.1%
All grid connections in our data341st of 7,9281,372,494 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Due to connect

Grid operator and place

More from California Independent System Operator Corporation

Other grid connections in Arizona

All 26 grid connections in Arizona, United States

Data on this page