Grid connection · the United Kingdom

Home Farm, Proposed Energy Storage @ grid connection

Home Farm, Proposed Energy Storage @ grid connection is a grid connection in the United Kingdom.

We hold more on this right.Capacity, connection date, grid operator, holder, location, queue date, status, technology and voltage: available on request.

Request this data

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
Name in the sourceHOME FARM, PROPOSED ENERGY STORAGE @ grid connectionNGED Connected Data portal · Terms not verified · checked 24 Oct 2026
LocationAvailable on requestNGED Connected Data portal · Terms not verified · checked 24 Oct 2026
StatusAvailable on requestNGED Connected Data portal · Terms not verified · checked 24 Oct 2026
HolderAvailable on requestNGED Connected Data portal · Terms not verified · checked 24 Oct 2026
CapacityAvailable on requestNGED Connected Data portal · Terms not verified · checked 24 Oct 2026
TechnologyAvailable on requestNGED Connected Data portal · Terms not verified · checked 24 Oct 2026
Grid operatorAvailable on requestNGED Connected Data portal · Terms not verified · checked 24 Oct 2026
Queue dateAvailable on requestNGED Connected Data portal · Terms not verified · checked 24 Oct 2026
Connection dateAvailable on requestNGED Connected Data portal · Terms not verified · checked 24 Oct 2026
VoltageAvailable on requestNGED Connected Data portal · Terms not verified · checked 24 Oct 2026
Coordinates53.0460, -2.0743NGED Connected Data portal · Terms not verified · checked 24 Oct 2026

Know more about this grid connection, or want an introduction to its owner? Ask us.

Nearby

Within 50 km of this grid connection: 306 power plants (86 operating, 663 MW), 11 data centers, 3 gas storage facilities, 3 substations and 1 transmission line, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Cellarhead Substation, Rownall Road - Battery Energy FacilityPower plant400 MWPermitted0.2 km
Newfields Farm, Rownall Road - Battery Energy StoragePower plant99.9 MWPermitted0.3 km
Cellarhead Substation, Rownall Road - Battery StoragePower plant2.6 MWPlanned0.5 km
Internet Central data center, EnglandData center——14 km
Salinae Hydrogen Storage projectGas storage facility—Planned28 km
Keuper Gas Storage ProjectGas storage facility—Permitted31 km
Keuper Underground Gas Storage Facility Material Change 1Gas storage facility—Planned32 km
Datum Datacentres (MCR2)Data center——39 km
HopeSubstation——39 km

Place

Other grid connections in United Kingdom

All 5913 grid connections in the United Kingdom

Data on this page