Grid connection · England, United Kingdom
Stoke Bardolph grid connection
Stoke Bardolph grid connection is a grid connection in England, United Kingdom.
We hold more on this right.Attached to, capacity, connection date, grid operator, holder, location, queue date, status, technology and voltage: available on request.
Request this dataFacts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Name in the source | STOKE BARDOLPH grid connection | NGED Connected Data portal · Terms not verified · checked 24 Oct 2026 |
| Location | Available on request | NGED Connected Data portal · Terms not verified · checked 24 Oct 2026 |
| Status | Available on request | NGED Connected Data portal · Terms not verified · checked 24 Oct 2026 |
| Holder | Available on request | NGED Connected Data portal · Terms not verified · checked 24 Oct 2026 |
| Attached to | Available on request | Rare Context entity resolution · CC0 1.0 · checked 24 Oct 2026 |
| Capacity | Available on request | NGED Connected Data portal · Terms not verified · checked 24 Oct 2026 |
| Technology | Available on request | NGED Connected Data portal · Terms not verified · checked 24 Oct 2026 |
| Grid operator | Available on request | NGED Connected Data portal · Terms not verified · checked 24 Oct 2026 |
| Queue date | Available on request | NGED Connected Data portal · Terms not verified · checked 24 Oct 2026 |
| Connection date | Available on request | NGED Connected Data portal · Terms not verified · checked 24 Oct 2026 |
| Voltage | Available on request | NGED Connected Data portal · Terms not verified · checked 24 Oct 2026 |
| Coordinates | 52.9233, -1.0179 | NGED Connected Data portal · Terms not verified · checked 24 Oct 2026 |
Know more about this grid connection, or want an introduction to its owner? Ask us.
Nearby
Within 50 km of this grid connection: 480 power plants (162 operating, 1,410 MW), 6 data centers, 2 transmission lines and 2 substations, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Heron Solar Farm & Battery Storage | Power plant | 20 MW | Permitted | 0.2 km |
| Heron Solar Farm & Battery Storage | Power plant | 20 MW | Permitted | 0.2 km |
| Cotgrave Solar Farm Battery | Power plant | 1 MW | Cancelled | 1.9 km |
| Experian | Data center | — | — | 9.8 km |
| Weston Marsh to East Leicestershire | Transmission line | — | Planned | 15 km |
| nLighten Nottingham | Data center | — | — | 16 km |
| Digital Space DC - Newark | Data center | — | — | 23 km |
| Chesterfield to Willington | Transmission line | — | Planned | 31 km |
| Kiveton Park | Substation | — | — | 48 km |
Place
Other grid connections in England
- Bute Hydrogen Project 1 grid connection4,800 MW
- Drax BECCS grid connection3,906 MW
- Drax Power Station grid connection3,906 MW
- Bute Hydrogen Project 2 grid connection3,600 MW
- Bute Hydrogen Project 3 grid connection3,600 MW
- Bute Hydrogen Project 5 grid connection3,600 MW
- Bute Hydrogen Project 6 grid connection3,600 MW
- Hinkley Point C grid connection3,340 MW
Data on this page
- DESNZ Renewable Energy Planning Database (REPD). DESNZ Renewable Energy Planning Database (REPD), Open Government Licence v3.0.
- NGED Connected Data portal. NGED Connected Data portal, Terms not verified.
- Supported by Northern Powergrid Open Data. Northern Powergrid open data portal, Northern Powergrid Open Data Licence v1.0.
- © OpenStreetMap contributors. OpenStreetMap data centers, ODbL 1.0.
- Planning Inspectorate: National Infrastructure Projects. Planning Inspectorate: National Infrastructure Projects, Open Government Licence v3.0.