Grid connection · England, United Kingdom
Chewton Mendip Shooters Bottom Solar Farm Townshead Lane grid connection
Chewton Mendip Shooters Bottom Solar Farm Townshead Lane grid connection is a grid connection in England, United Kingdom.
We hold more on this right.Attached to, capacity, connection date, grid operator, holder, location, status, technology and voltage: available on request.
Request this dataFacts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Name in the source | CHEWTON MENDIP SHOOTERS BOTTOM SOLAR FARM TOWNSHEAD LANE grid connection | NGED Connected Data portal · Terms not verified · checked 24 Oct 2026 |
| Location | Available on request | NGED Connected Data portal · Terms not verified · checked 24 Oct 2026 |
| Status | Available on request | NGED Connected Data portal · Terms not verified · checked 24 Oct 2026 |
| Holder | Available on request | NGED Connected Data portal · Terms not verified · checked 24 Oct 2026 |
| Attached to | Available on request | Rare Context entity resolution · CC0 1.0 · checked 24 Oct 2026 |
| Capacity | Available on request | NGED Connected Data portal · Terms not verified · checked 24 Oct 2026 |
| Technology | Available on request | NGED Connected Data portal · Terms not verified · checked 24 Oct 2026 |
| Grid operator | Available on request | NGED Connected Data portal · Terms not verified · checked 24 Oct 2026 |
| Connection date | Available on request | NGED Connected Data portal · Terms not verified · checked 24 Oct 2026 |
| Voltage | Available on request | NGED Connected Data portal · Terms not verified · checked 24 Oct 2026 |
| Coordinates | 51.2520, -2.5814 | NGED Connected Data portal · Terms not verified · checked 24 Oct 2026 |
Know more about this grid connection, or want an introduction to its owner? Ask us.
Nearby
Within 50 km of this grid connection: 458 power plants (198 operating, 1,578 MW), 52 substations, 9 data centers and 2 transmission lines, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Shooters Bottom Wind Park | Power plant | 2 MW | Operating | 0.3 km |
| Shooters Bottom Solar Park | Power plant | 7 MW | Operating | 0.8 km |
| Bays Lane, Gurney Slade - Solar Panels | Power plant | 2 MW | Planned | 4.2 km |
| Holwell Primary | Substation | — | — | 14 km |
| Hinkley Point C Connection | Transmission line | — | Permitted | 16 km |
| Bruton Primary | Substation | — | — | 18 km |
| Frome BSP | Substation | — | — | 19 km |
| Hinkley Point C Connection Project Material Change | Transmission line | — | Planned | 20 km |
| Insight Data Ltd | Data center | — | — | 26 km |
Place
Other grid connections in England
- Bute Hydrogen Project 1 grid connection4,800 MW
- Drax BECCS grid connection3,906 MW
- Drax Power Station grid connection3,906 MW
- Bute Hydrogen Project 2 grid connection3,600 MW
- Bute Hydrogen Project 3 grid connection3,600 MW
- Bute Hydrogen Project 5 grid connection3,600 MW
- Bute Hydrogen Project 6 grid connection3,600 MW
- Hinkley Point C grid connection3,340 MW
Data on this page
- DESNZ Renewable Energy Planning Database (REPD). DESNZ Renewable Energy Planning Database (REPD), Open Government Licence v3.0.
- NGED Connected Data portal. NGED Connected Data portal, Terms not verified.
- © OpenStreetMap contributors. OpenStreetMap data centers, ODbL 1.0.
- Planning Inspectorate: National Infrastructure Projects. Planning Inspectorate: National Infrastructure Projects, Open Government Licence v3.0.
- Rare Context entity resolution. Rare Context entity resolution, CC0 1.0.
- SSEN Distribution. SSEN Distribution data portal, CC BY 4.0.