Grid connection · England, United Kingdom

A019 Cotmoor grid connection

A019 Cotmoor grid connection is a grid connection in England, United Kingdom.

We hold more on this right.Capacity, connection date, grid operator, holder, location, queue date, status, technology and voltage: available on request.

Request this data

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
Name in the sourceA019 COTMOOR grid connectionNGED Connected Data portal · Terms not verified · checked 24 Oct 2026
LocationAvailable on requestNGED Connected Data portal · Terms not verified · checked 24 Oct 2026
StatusAvailable on requestNGED Connected Data portal · Terms not verified · checked 24 Oct 2026
HolderAvailable on requestNGED Connected Data portal · Terms not verified · checked 24 Oct 2026
CapacityAvailable on requestNGED Connected Data portal · Terms not verified · checked 24 Oct 2026
TechnologyAvailable on requestNGED Connected Data portal · Terms not verified · checked 24 Oct 2026
Grid operatorAvailable on requestNGED Connected Data portal · Terms not verified · checked 24 Oct 2026
Queue dateAvailable on requestNGED Connected Data portal · Terms not verified · checked 24 Oct 2026
Connection dateAvailable on requestNGED Connected Data portal · Terms not verified · checked 24 Oct 2026
VoltageAvailable on requestNGED Connected Data portal · Terms not verified · checked 24 Oct 2026
Coordinates53.0567, -0.9754NGED Connected Data portal · Terms not verified · checked 24 Oct 2026

Know more about this grid connection, or want an introduction to its owner? Ask us.

Nearby

Within 50 km of this grid connection: 471 power plants (141 operating, 1,385 MW), 65 substations, 5 data centers and 3 transmission lines, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Cotmoor LanePower plant49.9 MWPermitted0.6 km
Winkburn Estate Solar FarmPower plant49.9 MWUnder construction7.1 km
Farnsfield ADPower plant2 MWCancelled8.1 km
Digital Space DC - NewarkData center——12 km
nLighten NottinghamData center——17 km
ExperianData center——23 km
Weston Marsh to East LeicestershireTransmission line—Planned29 km
Chesterfield to WillingtonTransmission line—Planned31 km
StowSubstation——35 km

Place

Other grid connections in England

All 3831 grid connections in England, United Kingdom

Data on this page