Data center · Charleston County, South Carolina, United States
DartPoints Charleston
DartPoints Charleston is a data center in Charleston County, South Carolina, United States, operated by DartPoints.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Charleston County, South Carolina | OpenStreetMap data centers · record · ODbL 1.0 · checked 24 Oct 2026 |
| Address | 8480 Palmetto Commerce Parkway, Ladson, SC 29456 | OpenStreetMap data centers · record · ODbL 1.0 · checked 24 Oct 2026 |
| Operator | DartPoints | OpenStreetMap data centers · record · ODbL 1.0 · checked 24 Oct 2026 |
| Website | https://dartpoints.com/locations/chs01-charleston-sc/ | OpenStreetMap data centers · record · ODbL 1.0 · checked 24 Oct 2026 |
| Building footprint | 1,317 m² (building) | OpenStreetMap data centers · record · ODbL 1.0 · checked 24 Oct 2026 |
| Coordinates | 32.9649, -80.1013 | OpenStreetMap data centers · record · ODbL 1.0 · checked 24 Oct 2026 |
Research on this data center and its operator.Who owns it up to the parent company, its power supply, grid connection and planning status, and an introduction to the operator.
Request researchHow its operator compares
DartPoints operates 10 of the 1,336 data centers in the United States in our data with a named owner; 22 owners have more. Counts cover the data centers in our data that name an owner, holder or operator; an asset with several owners counts for each.
| Operator in United States | Rank | Data centers | Share |
|---|---|---|---|
| Amazon Web Services | 1st | 149 | 11% |
| Digital Realty | 2nd | 87 | 6.5% |
| Microsoft | 3rd | 66 | 4.9% |
| Amazon Data Services Inc. | 4th | 60 | 4.5% |
| 5th | 58 | 4.3% | |
| DartPoints | 23rd | 10 | 0.75% |
Nearby
Within 50 km of this data center: 3 power plants (2 operating, 3,111 MW) and 1 mine, measured from the coordinates in the facts above.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Williams | Power plant | 660 MW | Operating | 17 km |
| Pinopolis BESS | Power plant | 300 MW | Planned | 33 km |
| Diamond Mine #3 | Mine | — | Operating | 33 km |
| Cross | Power plant | 2,452 MW | Operating | 45 km |
Operator and place
More from DartPoints
- DartPoints Columbiadata center
- DartPoints Baton Rouge 2data center
- DartPoints Baton Rouge 1data center
- DartPoints Shreveportdata center
- DartPoints Dublindata center
- DartPoints Cincinnatidata center
- DartPoints Greenvilledata center
- DartPoints Spartanburgdata center
Other data centers in South Carolina
Data on this page
- Source: U.S. Energy Information Administration (Sep 2026). EIA-860 / 860M / 923, Public domain.
- Epoch AI. Epoch AI data centers, CC BY 4.0.
- MSHA Mines Data Set. MSHA Mines Data Set, Public domain.
- © OpenStreetMap contributors. OpenStreetMap data centers, ODbL 1.0.
- Texas Comptroller qualifying data centers. Texas Comptroller qualifying data centers, Public domain.
- Virginia DEQ issued data center air permits. Virginia DEQ issued data center air permits, Public records.