Data center · England, United Kingdom
The Bidder Street development
The Bidder Street development is a data center under construction in England, United Kingdom, operated by sineQN.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | England | OpenStreetMap data centers · record · ODbL 1.0 · checked 24 Oct 2026 |
| Status | Under construction | OpenStreetMap data centers · record · ODbL 1.0 · checked 24 Oct 2026 |
| Operator | sineQN | OpenStreetMap data centers · record · ODbL 1.0 · checked 24 Oct 2026 |
| Website | https://bidderstreetdatacentre.com | OpenStreetMap data centers · record · ODbL 1.0 · checked 24 Oct 2026 |
| Building footprint | 18,718 m² (site outline) | OpenStreetMap data centers · record · ODbL 1.0 · checked 24 Oct 2026 |
| Coordinates | 51.5168, 0.0030 | OpenStreetMap data centers · record · ODbL 1.0 · checked 24 Oct 2026 |
Research on this data center and its operator.Who owns it up to the parent company, its power supply, grid connection and planning status, and an introduction to the operator.
Request researchNearby
Within 50 km of this data center: 371 power plants (127 operating, 2,116 MW), 78 substations, 36 grid connections (22 operating, 233 MW), 1 transmission line and 1 AI supercomputer, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Bywaters’ Materials Recovery Facility Solar Array | Power plant | 1 MW | Operating | 0.8 km |
| The O2 Arena - Wind turbines | Power plant | 3 MW | Permitted | 1.7 km |
| Hedgehog Grove Solar Farm - Solar Panels | Power plant | 98 MW | Planned | 2.0 km |
| Solar 6.935 MW grid connection at Maiden Newton | Grid connection | 6.94 MW | Operating | 5.5 km |
| Tertiary Study grid connection | Grid connection | 57 MW | Planned | 6.4 km |
| North London (Electricity Line) Reinforcement | Transmission line | — | Permitted | 10 km |
| Ariel Way White City London grid connection | Grid connection | 2.2 MW | Operating | 16 km |
| Goldsmiths Primary | Substation | — | — | 18 km |
| Volt Avenue Primary | Substation | — | — | 18 km |
Operator and place
Other data centers in England
Data on this page
- DESNZ Renewable Energy Planning Database (REPD). DESNZ Renewable Energy Planning Database (REPD), Open Government Licence v3.0.
- © OpenStreetMap contributors. OpenStreetMap data centers, ODbL 1.0.
- Planning Inspectorate: National Infrastructure Projects. Planning Inspectorate: National Infrastructure Projects, Open Government Licence v3.0.
- SSEN Distribution. SSEN Distribution data portal, CC BY 4.0.