Substation · Sittard-Geleen, Limburg, Netherlands

Hoogspanningsstation DSM-2 Kerensheide (DSM-2 Kerensheide substation)

Hoogspanningsstation DSM-2 Kerensheide is a 150 kV substation in Sittard-Geleen, Limburg, Netherlands, operated by DSM/Chemelot.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationLimburgOpenStreetMap power infrastructure (Overpass) · record · ODbL 1.0, © OpenStreetMap contributors · checked 24 Oct 2026
LocationSittard-Geleen (point in boundary)PDOK Bestuurlijke Gebieden (Kadaster) · CC BY 4.0 · checked 25 Oct 2026
OperatorDSM/ChemelotOpenStreetMap power infrastructure (Overpass) · record · ODbL 1.0, © OpenStreetMap contributors · checked 24 Oct 2026
Voltage150 kV (levels 150, 30 kV)OpenStreetMap power infrastructure (Overpass) · record · ODbL 1.0, © OpenStreetMap contributors · checked 24 Oct 2026
Coordinates50.9735, 5.7933OpenStreetMap power infrastructure (Overpass) · record · ODbL 1.0, © OpenStreetMap contributors · checked 24 Oct 2026

Research on this substation and the land around it.Its headroom, connection queue and congestion, who owns the land around it, and an introduction to those owners.

Request research

How its operator compares

DSM/Chemelot operates 3 of the 440 substations in the Netherlands in our data with a named owner; 2 owners have more. Counts cover the substations in our data that name an owner, holder or operator; an asset with several owners counts for each.

Operator in NetherlandsRankSubstationsShare
TenneT1st42797%
ProRail2nd61.4%
DSM/Chemelot3rd30.68%
Stedin3rd30.68%
EdgeConnex5th20.45%

Nearby

Within 50 km of this substation: 416 permit notices, 258 power plants (172 operating, 4,791 MW), 13 CO2 emitters (9 operating), 10 data centers and 1 processing plant, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
SwentiboldcentralePower plant230 MWOperating1.3 km
Industry omgevingsvergunning decision, Sittard-Geleen (prb-2025-7813)Permit notice——1.3 km
Industry omgevingsvergunning application, Sittard-Geleen (prb-2025-4541)Permit notice——1.3 km
Industry omgevingsvergunning decision, Sittard-Geleen (prb-2025-12158)Permit notice——1.3 km
Solar Geleen (F&S solarfield Louisegroeve)Power plant3.37 MWOperating1.5 km
Solar Geleen (Helwig Vastgoed)Power plant1.29 MWOperating1.9 km
Chemelot BKG 01CO2 emitter2,820,546 tCO2e—2.0 km
Heat pump Brunssum (Stichting Weller Wonen)CO2 emitter—Operating12 km
Electric boiler Maastricht (Sappi Maastricht)CO2 emitter—Operating14 km

Operator and place

More from DSM/Chemelot

Candidate sites around this substation

3 sites of land near 150 kV DSM-2 Kerensheide have it as nearest substation. Each site page gives its area, its distance to the substation and its site score; owners are on request.

Other substations in Limburg

All 66 substations in Limburg, Netherlands

Data on this page