Substation · North Rhine-Westphalia, Germany
Station Gronau
Station Gronau is a 220 kV substation in North Rhine-Westphalia, Germany, connected by Amprion GmbH.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | North Rhine-Westphalia | OpenStreetMap power infrastructure (Overpass) · record · ODbL 1.0, © OpenStreetMap contributors · checked 24 Oct 2026 |
| Grid operator | Amprion GmbH | OpenStreetMap power infrastructure (Overpass) · record · ODbL 1.0, © OpenStreetMap contributors · checked 24 Oct 2026 |
| Voltage | 220 kV | OpenStreetMap power infrastructure (Overpass) · record · ODbL 1.0, © OpenStreetMap contributors · checked 24 Oct 2026 |
| Coordinates | 52.2030, 7.0349 | OpenStreetMap power infrastructure (Overpass) · record · ODbL 1.0, © OpenStreetMap contributors · checked 24 Oct 2026 |
Research on this substation and its grid operator.Who owns it up to the parent company, its headroom, congestion and the land around it, and an introduction to the grid operator.
Request researchNearby
Within 50 km of this substation: 289 power plants (174 operating, 2,824 MW), 257 permit notices, 15 CO2 emitters (10 operating) and 5 data centers, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Gronau Epe | Power plant | 11 MW | Operating | 4.0 km |
| Solar Overdinkel (KS NL7) | Power plant | 4.49 MW | Operating | 5.5 km |
| Bürgerwind Ammert | Power plant | 12 MW | Planned | 5.9 km |
| Substation omgevingsvergunning application, Enschede (prb-2026-7426) | Permit notice | — | — | 9.9 km |
| Industry omgevingsvergunning application, Enschede (prb-2026-7317) | Permit notice | — | — | 11 km |
| Solar park omgevingsvergunning decision, Enschede (gmb-2025-109658) | Permit notice | — | — | 13 km |
| Equinix Enschede | Data center | — | — | 13 km |
| Biomass heat Hengelo Ov (Warmtebedrijf Hengelo) | CO2 emitter | — | Operating | 20 km |
| Green gas Fleringen (Porkwatt) | CO2 emitter | — | Operating | 25 km |
Grid operator and place
More from Amprion GmbH
- Aach substationsubstation
- Station Arpesubstation
- Arpe/Halbeswig substationsubstation
- Bischofsheim substationsubstation
- Brauweiler substationsubstation
- Station Büscherhofsubstation
- Umspannwerk Dettingensubstation
- Station Eibergsubstation
Other substations in North Rhine-Westphalia
Data on this page
- Bundesnetzagentur, Marktstammdatenregister. Marktstammdatenregister, DL-DE-BY-2.0.
- Officiële Bekendmakingen. Officiële Bekendmakingen, CC0 1.0.
- © OpenStreetMap contributors. OpenStreetMap data centers, ODbL 1.0.
- OpenStreetMap power infrastructure (Overpass). OpenStreetMap power infrastructure (Overpass), ODbL 1.0, © OpenStreetMap contributors.
- RVO SDE(+)(+) projecten in beheer and SDE viewer. RVO SDE(+)(+) projecten in beheer and SDE viewer, Free reuse, no attribution required.