Substation · Berlin, Germany

Planned substation (search area Stadtbezirke Mitte/Reinickendorf)

Planned substation (search area Stadtbezirke Mitte/Reinickendorf) is a planned 380 kV substation in Berlin, Germany, connected by 50Hertz Transmission GmbH.

We hold more on this asset.Planned reinforcement: available on request.

Request this data

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationBerlinNetzentwicklungsplan Strom: digital project library · CC BY 4.0 · checked 24 Oct 2026
StatusPlannedNetzentwicklungsplan Strom: digital project library · CC BY 4.0 · checked 24 Oct 2026
Grid operator50Hertz Transmission GmbHNetzentwicklungsplan Strom: digital project library · CC BY 4.0 · checked 24 Oct 2026
Planned reinforcement380 kV shunt reactor (2x 176 Mvar) (due 2038, transmission network, NEP measure M685aa, project P360, added by this plan)Netzentwicklungsplan Strom: digital project library · CC BY 4.0 · checked 24 Oct 2026
Voltage380 kVNetzentwicklungsplan Strom: digital project library · CC BY 4.0 · checked 24 Oct 2026

Know more about this substation, or want an introduction to its grid operator? Ask us.

Grid operator and place

More from 50Hertz Transmission GmbH

Other substations in Berlin

All 143 substations in Berlin, Germany

Data on this page