Substation · Rickenbach, Baden-Württemberg, Germany
Kühmoos substation
Kühmoos substation is a 380 kV substation in Rickenbach, Baden-Württemberg, Germany, connected by TransnetBW GmbH.
We hold more on this substation.New connections, demand headroom, earliest connection and generation headroom: available on request.
Request this dataFacts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Baden-Württemberg | Netzentwicklungsplan Strom: digital project library · CC BY 4.0 · checked 24 Oct 2026 OpenStreetMap power infrastructure (Overpass) · record · ODbL 1.0, © OpenStreetMap contributors · checked 24 Oct 2026 |
| Location | Rickenbach (point in boundary) | BKG Verwaltungsgebiete 1:250 000 (VG250) · DL-DE-BY-2.0 · checked 25 Oct 2026 |
| Grid operator | TransnetBW GmbH | Netzentwicklungsplan Strom: digital project library · CC BY 4.0 · checked 24 Oct 2026 OpenStreetMap power infrastructure (Overpass) · record · ODbL 1.0, © OpenStreetMap contributors · checked 24 Oct 2026 |
| Demand headroom | Available on request | TransnetBW Netzanschlusskarte · Restricted · checked 25 Oct 2026 |
| Generation headroom | Available on request | TransnetBW Netzanschlusskarte · Restricted · checked 25 Oct 2026 |
| New connections | Available on request | TransnetBW Netzanschlusskarte · Restricted · checked 25 Oct 2026 Amprion: potential grid connection points (Reifegradverfahren) · Restricted · checked 25 Oct 2026 |
| Earliest connection | Available on request | TransnetBW Netzanschlusskarte · Restricted · checked 25 Oct 2026 Amprion: potential grid connection points (Reifegradverfahren) · Restricted · checked 25 Oct 2026 |
| Planned reinforcement | E-STATCOM (due 2037, transmission network, NEP measure M17h5, project P90, added by this plan) | Netzentwicklungsplan Strom: digital project library · CC BY 4.0 · checked 24 Oct 2026 |
| Planned reinforcement | Measure in the grid development plan (due 2036, transmission network, NEP measure M700, project TNG-P428, start grid (approved or under way)) | Netzentwicklungsplan Strom: digital project library · record · CC BY 4.0 · checked 24 Oct 2026 |
| Planned reinforcement | MSCDN (due 2032, transmission network, NEP measure M17g7, project TNG-P90, start grid (approved or under way), confirmed by the previous plan) | Netzentwicklungsplan Strom: digital project library · CC BY 4.0 · checked 24 Oct 2026 |
| Voltage | 380 kV (levels 380, 220 kV) | OpenStreetMap power infrastructure (Overpass) · record · ODbL 1.0, © OpenStreetMap contributors · checked 24 Oct 2026 |
| Coordinates | 47.5960, 7.9578 | OpenStreetMap power infrastructure (Overpass) · record · ODbL 1.0, © OpenStreetMap contributors · checked 24 Oct 2026 |
Know more about this substation? Ask us.
Also recorded as
4 sources record Kühmoos substation; this page joins their facts, each with its own source. Links to any of the records lead here. How records are matched.
| Name in the source | Identifier | Source | Matched on |
|---|---|---|---|
| Kühmoos substation | asset:nep:kuhmoos | Netzentwicklungsplan Strom: digital project library | — |
| Netzknoten Kühmoos | asset:osm:way-88916034 | OpenStreetMap power infrastructure (Overpass) | Same name and Land |
| Kühmoos substation | asset:transnetbw:kuehmoos | TransnetBW Netzanschlusskarte | Same name and Land |
| Kühmoos substation | asset:amprion:kuhmoos | Amprion: potential grid connection points (Reifegradverfahren) | Same name and Land |
Nearby
Within 50 km of this substation: 63 power plants (26 operating, 11,484 MW), measured from the coordinates in the facts above. The table shows the nearest 3.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| WKW Säckingen | Power plant | 69 MW | Operating | 4.3 km |
| Säckingen power station | Power plant | 73.6 MW | — | 4.3 km |
| BESS Wehr – 11,5 MW | Power plant | 11.5 MW | Planned | 4.4 km |
Grid operator and place
More from TransnetBW GmbH
- Umspannwerk Altlußheimsubstation
- Karlsruhe-Daxlandensubstation
- Dellmensingensubstation
- 380-kV-Umspannwerk Eichstettensubstation
- Herbertingen substationsubstation
- Umspannwerk Höpfingensubstation
- Umspannwerk Hüffenhardtsubstation
- Umspannwerk Kupferzellsubstation
Other substations in Baden-Württemberg
Data on this page
- Amprion: potential grid connection points (Reifegradverfahren). Amprion: potential grid connection points (Reifegradverfahren), Restricted.
- © BKG (2026) dl-de/by-2-0, Datenquellen: https://sg.geodatenzentrum.de/web_public/gdz/datenquellen/datenquellen_vg_nuts.pdf. BKG Verwaltungsgebiete 1:250 000 (VG250), DL-DE-BY-2.0.
- Bundesnetzagentur, Marktstammdatenregister. Marktstammdatenregister, DL-DE-BY-2.0.
- Netzentwicklungsplan Strom 2037/2045 (2025), zweiter Entwurf | Übertragungsnetzbetreiber (M) CC-BY-4.0. Netzentwicklungsplan Strom: digital project library, CC BY 4.0.
- OpenStreetMap power infrastructure (Overpass). OpenStreetMap power infrastructure (Overpass), ODbL 1.0, © OpenStreetMap contributors.
- TransnetBW Netzanschlusskarte. TransnetBW Netzanschlusskarte, Restricted.
- Wikidata. Wikidata, CC0 1.0.