300 ha site at Gemarkung Klein Partwitz Flur 1, Flurstück 189/1
A candidate site of 300 ha in Saxony, made up of 1 cadastral parcel, mostly open-cast mine or quarry. It lies 1.56 km from the 110 kV substation Umspannstation Proschim (UKA Netz GmbH). The nearest transmission substation, Umspannwerk Altdöbern (380 kV), is 18.6 km away, where the grid development plan lists 3 measures.
Owner, grid capacity and planning status on request.We do not publish owners: the German land register (Grundbuch) is not public. Ask us and we find out who owns these parcels, the free capacity at the nearest substation and the zoning that applies, and whether the site is available.
Request owner, grid and planningFacts
Every value links to its source. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Area | 300 ha (the official areas of its parcels added up) | Rare Context powered-land sites · ODbL 1.0 · checked 24 Oct 2026 |
| Cadastral parcels | 1 (largest: Gemarkung Klein Partwitz Flur 1, Flurstück 189/1) | ALKIS Sachsen (open cadastre) · Free of charge with the source credited · checked 24 Oct 2026 |
| Land use | Open-cast mine or quarry (Tagebau, Grube, Steinbruch) (100% of the area, as the cadastre records it) | Rare Context powered-land sites · ODbL 1.0 · checked 24 Oct 2026 |
| Location | Saxony | Rare Context powered-land sites · ODbL 1.0 · checked 24 Oct 2026 |
| Coordinates | 51.5222, 14.1939 (a point on the largest parcel) | Rare Context powered-land sites · ODbL 1.0 · checked 24 Oct 2026 |
| Nearest substation | Umspannstation Proschim (1.56 km, site edge to substation fence) | Rare Context powered-land sites · ODbL 1.0 · checked 24 Oct 2026 |
| Substation voltage | 110 kV | OpenStreetMap power infrastructure (Overpass) · record · ODbL 1.0, © OpenStreetMap contributors · checked 24 Oct 2026 |
| Substation operator | UKA Netz GmbH | OpenStreetMap power infrastructure (Overpass) · record · ODbL 1.0, © OpenStreetMap contributors · checked 24 Oct 2026 |
| Nearest transmission substation | Umspannwerk Altdöbern (18.6 km from the nearest parcel, 380 kV, 50Hertz Transmission GmbH) | Rare Context powered-land sites · ODbL 1.0 · checked 24 Oct 2026 |
| Planned at that substation | 380 kV shunt reactor (1x 176 Mvar) (due 2030) (Netzentwicklungsplan; 2 more measures available on request) | Netzentwicklungsplan Strom: digital project library · CC BY 4.0 · checked 24 Oct 2026 |
How it compares
#97 of 264 sites in Saxony and #2,006 of 4,863 in Germany by site score. Larger than 98% of the sites in Saxony. Closer to its substation than 24% of them.
| Part | This site | Points | Of |
|---|---|---|---|
| Area | 300 ha | 35 | 35 |
| Distance to the substation | 1.56 km | 7.7 | 35 |
| Substation voltage | 110 kV | 10 | 30 |
| Site score | 53 | 100 |
How the site score works in Germany · Search sites in Saxony
Nearby sites on the same substation
1 other site has Umspannstation Proschim as nearest substation and would compete for its capacity.
- 50 ha site at Gemarkung Lieske, Flur 2, Flurstück 1880.21 km · score 57
- Sites in Saxony272
- Sites in Germany5,000
- Umspannstation Proschimsubstation
Data on this page
- ALKIS Sachsen (open cadastre). ALKIS Sachsen (open cadastre), Free of charge with the source credited.
- Netzentwicklungsplan Strom: point measures (Punktmaßnahmen). Netzentwicklungsplan Strom: point measures (Punktmaßnahmen), Restricted.
- Netzentwicklungsplan Strom 2037/2045 (2025), zweiter Entwurf | Übertragungsnetzbetreiber (M) CC-BY-4.0. Netzentwicklungsplan Strom: digital project library, CC BY 4.0.
- OpenStreetMap power infrastructure (Overpass). OpenStreetMap power infrastructure (Overpass), ODbL 1.0, © OpenStreetMap contributors.
- Rare Context. Rare Context powered-land sites, ODbL 1.0.