Power plant · Dronten, Flevoland, Netherlands

Windpark Vires Venti

Windpark Vires Venti is a power plant in Dronten, Flevoland, Netherlands, with 19 MW of capacity, operated by Windpark Vires Venti B.V.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationDrontenRVO SDE(+)(+) projecten in beheer and SDE viewer · Free reuse, no attribution required · checked 24 Oct 2026
StatusOperatingRVO SDE(+)(+) projecten in beheer and SDE viewer · Free reuse, no attribution required · checked 24 Oct 2026
Start year2023RVO SDE(+)(+) projecten in beheer and SDE viewer · Free reuse, no attribution required · checked 24 Oct 2026
Onshore or offshoreOnshoreRVO SDE(+)(+) projecten in beheer and SDE viewer · Free reuse, no attribution required · checked 24 Oct 2026
OperatorWindpark Vires Venti B.V.RVO SDE(+)(+) projecten in beheer and SDE viewer · Free reuse, no attribution required · checked 24 Oct 2026
Capacity19 MWRVO SDE(+)(+) projecten in beheer and SDE viewer · Free reuse, no attribution required · checked 24 Oct 2026
TechnologyWindRVO SDE(+)(+) projecten in beheer and SDE viewer · Free reuse, no attribution required · checked 24 Oct 2026
Coordinates52.5234, 5.7254RVO SDE(+)(+) projecten in beheer and SDE viewer · Free reuse, no attribution required · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

How it compares

Windpark Vires Venti is the 37th-largest of 116 power plants in Flevoland and the 239th-largest of 2,153 in the Netherlands by capacity; its 19 MW is <0.1% of the 37,557 MW we hold for the Netherlands. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.

WithinRankTotalShare
Flevoland37th of 1163,507 MW0.54%
Netherlands239th of 2,15337,557 MW<0.1%
All power plants in our data4,517th of 12,7051,210,931 MW<0.1%

Nearby

Within 50 km of this power plant: 762 permit notices, 58 substations, 33 CO2 emitters (24 operating), 7 data centers and 1 processing plant, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Solcon DrotenData center——2.4 km
Kolo NL1 DrontenData center——2.6 km
150 kV Windplan GroenSubstation——4.0 km
150 kV OlsterpadSubstation——4.1 km
150 kV DrontenSubstation——4.3 km
Nitrogen natuurvergunning decision, Dronten (prb-2025-18646)Permit notice——8.1 km
Nitrogen natuurvergunning application, Dronten (prb-2026-10475)Permit notice——8.6 km
Green gas Biddinghuizen (De Torenhoeve Biogas)CO2 emitter—Operating10.0 km
Nitrogen natuurvergunning application, Dronten (prb-2025-18469)Permit notice——11 km

Operator and place

Other power plants in Flevoland

All 129 power plants in Flevoland, Netherlands