Permit notice · Rotterdam, South Holland, Netherlands
Industry omgevingsvergunning draft decision, Rotterdam (prb-2024-17783)
Industry omgevingsvergunning draft decision, Rotterdam (prb-2024-17783) is a permit notice in Rotterdam, South Holland, Netherlands, published 20 Nov 2024, applied for by Expresso B.V. and Bilfinger Tebodin Netherlands B.V.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Rotterdam | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Permit date | 20 Nov 2024 (omgevingsvergunning) | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Notice type | Draft decision | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Applicant | Expresso B.V. | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Applicant | Bilfinger Tebodin Netherlands B.V. | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Technology | Industry | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Coordinates | 51.8933, 4.4612 | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
Research on this permit notice and its holder.Who holds it up to the parent company, the decision and the asset it is for, and an introduction to the holder.
Request researchLatest events
Dated events about this permit notice from official notices and registers, newest first. All recent changes.
- Draft decision (environmental permit) · source
Nearby
Within 50 km of this permit notice: 596 power plants (475 operating, 10,268 MW), 149 substations, 86 CO2 emitters (45 operating), 47 data centers and 2 processing plants, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| 150 kV Rotterdam Centrum | Substation | — | — | 1.2 km |
| Solar Rotterdam (Den Hartogh Liquid Logistics) | Power plant | 1.01 MW | Operating | 1.4 km |
| Solar Rotterdam (Sunrock Assets XII) | Power plant | 2.26 MW | Operating | 1.7 km |
| Solar Rotterdam (Eneco Solar) | Power plant | 1.97 MW | Operating | 2.0 km |
| NorthC Datacenter Rotterdam Waalhaven | Data center | — | — | 2.2 km |
| Electric boiler Rotterdam (Air Liquide Industrie) | CO2 emitter | — | Cancelled | 2.4 km |
| Urban Mining Factory - Printed Circuit Boards | Processing plant | — | — | 2.7 km |
| 150 kV substation (OSM way/129650358) | Substation | — | — | 2.7 km |
| 150 kV Rotterdam Waalhaven | Substation | — | — | 2.8 km |
Place
Other permit notices in South Holland
- Battery storage omgevingsplan application, Midden-Delfland (gmb-2026-166439)
- Battery storage omgevingsplan application, Nieuwkoop (gmb-2026-286452)
- Battery storage omgevingsplan application, Rotterdam (gmb-2026-427260)
- Battery storage omgevingsplan decision, Kaag en Braassem (gmb-2025-123830)
- Battery storage omgevingsplan decision, Kaag en Braassem (gmb-2026-395920)
- Battery storage omgevingsplan decision, Lisse (gmb-2026-93012)
- Battery storage omgevingsplan decision, Midden-Delfland (gmb-2026-210961)
- Battery storage omgevingsplan decision, Nieuwkoop (gmb-2026-346519)
Data on this page
- © European Union, European Commission (DG GROW). EU CRMA strategic projects, CC BY 4.0.
- Officiële Bekendmakingen. Officiële Bekendmakingen, CC0 1.0.
- © OpenStreetMap contributors. OpenStreetMap data centers, ODbL 1.0.
- OpenStreetMap power infrastructure (Overpass). OpenStreetMap power infrastructure (Overpass), ODbL 1.0, © OpenStreetMap contributors.
- RVO SDE(+)(+) projecten in beheer and SDE viewer. RVO SDE(+)(+) projecten in beheer and SDE viewer, Free reuse, no attribution required.