Permit notice · Amsterdam, North Holland, Netherlands
Substation omgevingsvergunning decision, Amsterdam (prb-2025-14128)
Substation omgevingsvergunning decision, Amsterdam (prb-2025-14128) is a permit notice in Amsterdam, North Holland, Netherlands, published 1 Sept 2025, applied for by Global Switch Amsterdam B.V.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Amsterdam | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Permit date | 1 Sept 2025 (omgevingsvergunning) | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Notice type | Decision | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Applicant | Global Switch Amsterdam B.V. | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Technology | Substation | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Coordinates | 52.3440, 4.8289 | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
Research on this permit notice and its holder.Who holds it up to the parent company, the decision and the asset it is for, and an introduction to the holder.
Request researchLatest events
Dated events about this permit notice from official notices and registers, newest first. All recent changes.
- Permit granted (environmental permit) · source
Nearby
Within 50 km of this permit notice: 411 power plants (326 operating, 5,418 MW), 101 substations, 89 data centers, 69 CO2 emitters (39 operating) and 2 AI supercomputers, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Global Switch Amsterdam | Data center | — | — | 0.0 km |
| Data center, Amsterdam (OSM way 700738101) | Data center | — | — | 0.1 km |
| 150 kV Nieuwe Meer | Substation | — | — | 1.3 km |
| Solar Amstelveen (Sun Invest Holding) | Power plant | 4.77 MW | Planned | 3.1 km |
| Data center, Amsterdam (OSM way 883367894) | Data center | — | — | 4.0 km |
| 150 kV Zorgvlied | Substation | — | — | 4.1 km |
| Solar Amsterdam (GLP NL Solar) | Power plant | 2.26 MW | Operating | 4.5 km |
| Solar Schiphol (Koninklijke Luchtvaart Maatschappij) | Power plant | 2.06 MW | Operating | 4.5 km |
| Residual heat Oude Meer (Do Spierynck Meer) | CO2 emitter | — | Cancelled | 6.6 km |
Place
Other permit notices in North Holland
- Battery storage omgevingsplan application, Schagen (gmb-2025-189435)
- Battery storage omgevingsplan application, Schagen (gmb-2025-332860)
- Battery storage omgevingsplan decision, Amstelveen (gmb-2026-219541)
- Battery storage omgevingsplan decision, Schagen (gmb-2025-315647)
- Battery storage omgevingsplan decision, Schagen (gmb-2025-369965)
- Battery storage omgevingsvergunning application, Alkmaar (gmb-2025-410489)
- Battery storage omgevingsvergunning application, Alkmaar (gmb-2026-309630)
- Battery storage omgevingsvergunning application, Amstelveen (gmb-2025-487143)
Data on this page
- Officiële Bekendmakingen. Officiële Bekendmakingen, CC0 1.0.
- © OpenStreetMap contributors. OpenStreetMap data centers, ODbL 1.0.
- OpenStreetMap power infrastructure (Overpass). OpenStreetMap power infrastructure (Overpass), ODbL 1.0, © OpenStreetMap contributors.
- RVO SDE(+)(+) projecten in beheer and SDE viewer. RVO SDE(+)(+) projecten in beheer and SDE viewer, Free reuse, no attribution required.