Permit notice · Haarlemmermeer, North Holland, Netherlands
Data center omgevingsvergunning decision, Haarlemmermeer (prb-2025-124)
Data center omgevingsvergunning decision, Haarlemmermeer (prb-2025-124) is a permit notice in Haarlemmermeer, North Holland, Netherlands, published 6 Jan 2025, applied for by EdgeConneX AMS06 B.V.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Haarlemmermeer | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Permit date | 6 Jan 2025 (omgevingsvergunning) | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Notice type | Decision | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Applicant | EdgeConneX AMS06 B.V. | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Attached to | EdgeConneX AMS06 (matched by applicant+site code+municipality) | Rare Context entity resolution · CC0 1.0 · checked 24 Oct 2026 |
| Technology | Data center | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Coordinates | 52.2830, 4.7421 | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
Research on this permit notice and its holder.Who holds it up to the parent company, the decision and the asset it is for, and an introduction to the holder.
Request researchLatest events
Dated events about this permit notice from official notices and registers, newest first. All recent changes.
- Permit granted (environmental permit) · source
Nearby
Within 50 km of this permit notice: 421 power plants (330 operating, 4,862 MW), 120 substations, 89 data centers, 80 CO2 emitters (44 operating), 2 AI supercomputers and 2 processing plants, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| EdgeConneX AMS06 | Data center | — | — | 0.0 km |
| NTT Amsterdam 1 Data Center | Data center | — | — | 0.2 km |
| Solar Rozenburg Nh (International Solar Projects III) | Power plant | 3.37 MW | Operating | 0.7 km |
| Digital Realty AMS8 | Data center | — | — | 0.7 km |
| Solar Schiphol (Eneco Solar) | Power plant | 8 MW | Cancelled | 0.8 km |
| Residual heat Rozenburg Nh (Polderwarmte R&S) | CO2 emitter | — | Cancelled | 1.1 km |
| 150 kV substation (OSM way/1320723204) | Substation | — | — | 1.2 km |
| Green gas Rijsenhout (De Meerlanden Holding) | CO2 emitter | — | Operating | 1.6 km |
| Green gas Rijsenhout (Meerlanden Compostering) | CO2 emitter | — | Permitted | 1.6 km |
Place
Other permit notices in North Holland
- Battery storage omgevingsplan application, Schagen (gmb-2025-189435)
- Battery storage omgevingsplan application, Schagen (gmb-2025-332860)
- Battery storage omgevingsplan decision, Amstelveen (gmb-2026-219541)
- Battery storage omgevingsplan decision, Schagen (gmb-2025-315647)
- Battery storage omgevingsplan decision, Schagen (gmb-2025-369965)
- Battery storage omgevingsvergunning application, Alkmaar (gmb-2025-410489)
- Battery storage omgevingsvergunning application, Alkmaar (gmb-2026-309630)
- Battery storage omgevingsvergunning application, Amstelveen (gmb-2025-487143)
Data on this page
- Officiële Bekendmakingen. Officiële Bekendmakingen, CC0 1.0.
- © OpenStreetMap contributors. OpenStreetMap data centers, ODbL 1.0.
- OpenStreetMap power infrastructure (Overpass). OpenStreetMap power infrastructure (Overpass), ODbL 1.0, © OpenStreetMap contributors.
- Rare Context entity resolution. Rare Context entity resolution, CC0 1.0.
- RVO SDE(+)(+) projecten in beheer and SDE viewer. RVO SDE(+)(+) projecten in beheer and SDE viewer, Free reuse, no attribution required.