Data center omgevingsvergunning application, Amsterdam (prb-2026-6693)
Data center omgevingsvergunning application, Amsterdam (prb-2026-6693) is a permit notice in Amsterdam, North Holland, Netherlands, published 20 Apr 2026, applied for by Equinix (Netherlands) B.V.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Amsterdam | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Permit date | 20 Apr 2026 (omgevingsvergunning) | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Notice type | Application | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Applicant | Equinix (Netherlands) B.V. | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Technology | Data center | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Coordinates | 52.3372, 4.9337 | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
Research on this permit notice and its holder.Who holds it up to the parent company, the decision and the asset it is for, and an introduction to the holder.
Request researchLatest events
Dated events about this permit notice from official notices and registers, newest first. All recent changes.
- Permit applied for (environmental permit) · source
Nearby
Within 50 km of this permit notice: 445 power plants (352 operating, 6,223 MW), 98 substations, 89 data centers, 72 CO2 emitters (43 operating), 2 AI supercomputers and 1 processing plant, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Equinix AM6 | Data center | — | — | 0.0 km |
| Data center, Amsterdam (OSM way 279860375) | Data center | — | — | 0.1 km |
| Digital Realty AMS18 | Data center | — | — | 0.1 km |
| 110 kV substation (OSM way/1551706688) | Substation | — | — | 1.8 km |
| 150 kV Venserweg | Substation | — | — | 2.2 km |
| 150 kV Bijlmer Noord | Substation | — | — | 2.4 km |
| Solar Amsterdam (Stadion Amsterdam) | Power plant | 1.13 MW | Operating | 2.4 km |
| SURF Snellius Phase 1 | AI supercomputer | 91 H100e | Operating | 2.5 km |
| SURF Snellius Phase 3 | AI supercomputer | 443 H100e | Operating | 2.5 km |
Place
Other permit notices in North Holland
- Battery storage omgevingsplan application, Schagen (gmb-2025-189435)
- Battery storage omgevingsplan application, Schagen (gmb-2025-332860)
- Battery storage omgevingsplan decision, Amstelveen (gmb-2026-219541)
- Battery storage omgevingsplan decision, Schagen (gmb-2025-315647)
- Battery storage omgevingsplan decision, Schagen (gmb-2025-369965)
- Battery storage omgevingsvergunning application, Alkmaar (gmb-2025-410489)
- Battery storage omgevingsvergunning application, Alkmaar (gmb-2026-309630)
- Battery storage omgevingsvergunning application, Amstelveen (gmb-2025-487143)
Data on this page
- Epoch AI. Epoch AI supercomputers, CC BY 4.0.
- Officiële Bekendmakingen. Officiële Bekendmakingen, CC0 1.0.
- © OpenStreetMap contributors. OpenStreetMap data centers, ODbL 1.0.
- OpenStreetMap power infrastructure (Overpass). OpenStreetMap power infrastructure (Overpass), ODbL 1.0, © OpenStreetMap contributors.
- RVO SDE(+)(+) projecten in beheer and SDE viewer. RVO SDE(+)(+) projecten in beheer and SDE viewer, Free reuse, no attribution required.