Permit notice · Amstelveen, North Holland, Netherlands
Battery storage omgevingsvergunning decision, Amstelveen (gmb-2025-531708)
Battery storage omgevingsvergunning decision, Amstelveen (gmb-2025-531708) is a permit notice in Amstelveen, North Holland, Netherlands, published 8 Dec 2025.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Amstelveen | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Permit date | 8 Dec 2025 (omgevingsvergunning) | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Notice type | Decision | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Technology | Battery storage | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Coordinates | 52.2863, 4.8799 | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
Research on this permit notice and its holder.Who holds it up to the parent company, the decision and the asset it is for, and an introduction to the holder.
Request researchLatest events
Dated events about this permit notice from official notices and registers, newest first. All recent changes.
- Permit granted (environmental permit) · source
Nearby
Within 50 km of this permit notice: 425 power plants (331 operating, 5,235 MW), 107 substations, 83 data centers, 71 CO2 emitters (38 operating), 2 AI supercomputers and 1 processing plant, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| 150 kV Amstelveen | Substation | — | — | 0.6 km |
| Solar Amstelveen (Waterschap Amstel, Gooi en Vecht) | Power plant | 1.27 MW | Operating | 3.2 km |
| Solar Amstelveen (Sun Invest Holding) | Power plant | 4.77 MW | Planned | 4.3 km |
| Verizon data center, Amsterdam | Data center | — | — | 4.3 km |
| Verizon 2 | Data center | — | — | 4.3 km |
| Equinix AM7 | Data center | — | — | 4.4 km |
| Solar Amstelveen (Agrimm) | Power plant | 1.16 MW | Operating | 4.7 km |
| 150 kV Bijlmer Zuid | Substation | — | — | 4.7 km |
| 150 kV Bijlmer Noord | Substation | — | — | 4.9 km |
Place
Other permit notices in North Holland
- Battery storage omgevingsplan application, Schagen (gmb-2025-189435)
- Battery storage omgevingsplan application, Schagen (gmb-2025-332860)
- Battery storage omgevingsplan decision, Amstelveen (gmb-2026-219541)
- Battery storage omgevingsplan decision, Schagen (gmb-2025-315647)
- Battery storage omgevingsplan decision, Schagen (gmb-2025-369965)
- Battery storage omgevingsvergunning application, Alkmaar (gmb-2025-410489)
- Battery storage omgevingsvergunning application, Alkmaar (gmb-2026-309630)
- Battery storage omgevingsvergunning application, Amstelveen (gmb-2025-487143)
Data on this page
- Officiële Bekendmakingen. Officiële Bekendmakingen, CC0 1.0.
- © OpenStreetMap contributors. OpenStreetMap data centers, ODbL 1.0.
- OpenStreetMap power infrastructure (Overpass). OpenStreetMap power infrastructure (Overpass), ODbL 1.0, © OpenStreetMap contributors.
- RVO SDE(+)(+) projecten in beheer and SDE viewer. RVO SDE(+)(+) projecten in beheer and SDE viewer, Free reuse, no attribution required.