Permit notice · Venlo, Limburg, Netherlands
Nitrogen natuurvergunning application, Venlo (prb-2025-3074)
Nitrogen natuurvergunning application, Venlo (prb-2025-3074) is a permit notice in Venlo, Limburg, Netherlands, published 28 Feb 2025.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Venlo | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Permit date | 28 Feb 2025 (natuurvergunning) | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Notice type | Application | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Technology | Nitrogen | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Coordinates | 51.3850, 6.1572 | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
Research on this permit notice and its holder.Who holds it up to the parent company, the decision and the asset it is for, and an introduction to the holder.
Request researchLatest events
Dated events about this permit notice from official notices and registers, newest first. All recent changes.
- Permit applied for (nature permit) · source
Nearby
Within 50 km of this permit notice: 439 power plants (293 operating, 5,460 MW), 192 substations, 36 CO2 emitters (17 operating), 8 data centers and 1 processing plant, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Solar Venlo (GLP NL Solar) | Power plant | 4.26 MW | Planned | 0.5 km |
| Systemec Venlo DC19 | Data center | — | — | 0.7 km |
| Systemec Venlo DC25 | Data center | — | — | 0.8 km |
| 150 kV Blerick | Substation | — | — | 1.0 km |
| Solar Venlo (Boreal Industrial DDP Propco 3) | Power plant | 1.51 MW | Cancelled | 1.1 km |
| Solar Venlo (Groendus Projects) | Power plant | 2.45 MW | Cancelled | 1.3 km |
| 150 kV Boekend | Substation | — | — | 3.1 km |
| 150 kV Californië | Substation | — | — | 5.6 km |
| Geothermal heat Grubbenvorst (Geobalanz) | CO2 emitter | — | Operating | 6.2 km |
Place
Other permit notices in Limburg
- Battery storage omgevingsvergunning application, Beek (gmb-2025-3841)
- Battery storage omgevingsvergunning application, Echt-Susteren (gmb-2025-514872)
- Battery storage omgevingsvergunning application, Echt-Susteren (gmb-2026-288455)
- Battery storage omgevingsvergunning application, Echt-Susteren (gmb-2026-288464)
- Battery storage omgevingsvergunning application, Heerlen (gmb-2025-258802)
- Battery storage omgevingsvergunning application, Heerlen (gmb-2026-376025)
- Battery storage omgevingsvergunning application, Landgraaf (gmb-2024-476613)
- Battery storage omgevingsvergunning application, Leudal (gmb-2025-567734)
Data on this page
- Officiële Bekendmakingen. Officiële Bekendmakingen, CC0 1.0.
- © OpenStreetMap contributors. OpenStreetMap data centers, ODbL 1.0.
- OpenStreetMap power infrastructure (Overpass). OpenStreetMap power infrastructure (Overpass), ODbL 1.0, © OpenStreetMap contributors.
- RVO SDE(+)(+) projecten in beheer and SDE viewer. RVO SDE(+)(+) projecten in beheer and SDE viewer, Free reuse, no attribution required.