Permit notice · Gulpen-Wittem, Limburg, Netherlands
Nitrogen natuurvergunning draft decision, Gulpen-Wittem (prb-2026-11976)
Nitrogen natuurvergunning draft decision, Gulpen-Wittem (prb-2026-11976) is a permit notice in Gulpen-Wittem, Limburg, Netherlands, published 15 Jul 2026.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Gulpen-Wittem | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Permit date | 15 Jul 2026 (natuurvergunning) | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Notice type | Draft decision | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Technology | Nitrogen | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Coordinates | 50.7959, 5.8227 | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
Research on this permit notice and its holder.Who holds it up to the parent company, the decision and the asset it is for, and an introduction to the holder.
Request researchLatest events
Dated events about this permit notice from official notices and registers, newest first. All recent changes.
- Draft decision (nature permit) · source
Nearby
Within 50 km of this permit notice: 154 power plants (98 operating, 3,843 MW), 90 substations, 11 data centers, 7 CO2 emitters (3 operating) and 1 processing plant, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Solar Cadier en Keer (Tramhof Storage) | Power plant | 1.68 MW | Operating | 4.4 km |
| Solar Maastricht (Sligro Food Group Nederland) | Power plant | 1.61 MW | Operating | 7.8 km |
| 150 kV Schoonbron | Substation | — | — | 7.9 km |
| Solar Maastricht (Coöperatie Maasstroom) | Power plant | 15.4 MW | Cancelled | 11 km |
| 150 kV Limmel | Substation | — | — | 11 km |
| Electric boiler Maastricht (Sappi Maastricht) | CO2 emitter | — | Operating | 11 km |
| Heidelberg Materials Benelux - Cimenterie Lixhe | CO2 emitter | 826,247 tCO2e | — | 12 km |
| Lixhe 380 kV | Substation | — | — | 12 km |
| Smartdc Heerlen | Data center | — | — | 15 km |
Place
Other permit notices in Limburg
- Battery storage omgevingsvergunning application, Beek (gmb-2025-3841)
- Battery storage omgevingsvergunning application, Echt-Susteren (gmb-2025-514872)
- Battery storage omgevingsvergunning application, Echt-Susteren (gmb-2026-288455)
- Battery storage omgevingsvergunning application, Echt-Susteren (gmb-2026-288464)
- Battery storage omgevingsvergunning application, Heerlen (gmb-2025-258802)
- Battery storage omgevingsvergunning application, Heerlen (gmb-2026-376025)
- Battery storage omgevingsvergunning application, Landgraaf (gmb-2024-476613)
- Battery storage omgevingsvergunning application, Leudal (gmb-2025-567734)
Data on this page
- Elia grid hosting capacity map. Elia grid hosting capacity map, Restricted.
- European Commission, Union Registry. EU Union Registry public data, CC BY 4.0.
- Officiële Bekendmakingen. Officiële Bekendmakingen, CC0 1.0.
- © OpenStreetMap contributors. OpenStreetMap data centers, ODbL 1.0.
- OpenStreetMap power infrastructure (Overpass). OpenStreetMap power infrastructure (Overpass), ODbL 1.0, © OpenStreetMap contributors.
- RVO SDE(+)(+) projecten in beheer and SDE viewer. RVO SDE(+)(+) projecten in beheer and SDE viewer, Free reuse, no attribution required.