| Fact | Value | Source |
|---|---|---|
| Location | Oldambt | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Permit date | 1 Oct 2025 (natuurvergunning) | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Notice type | Application | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Technology | Nitrogen | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Coordinates | 53.1538, 7.0881 | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
Research on this permit notice and its holder.Who holds it up to the parent company, the decision and the asset it is for, and an introduction to the holder.
Request researchLatest events
Dated events about this permit notice from official notices and registers, newest first. All recent changes.
- Permit applied for (nature permit) · source
Nearby
Within 50 km of this permit notice: 293 power plants (223 operating, 9,888 MW), 138 substations, 21 CO2 emitters (11 operating) and 8 data centers, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Solar Winschoten (Solarroofs Nederland) | Power plant | 5.46 MW | Cancelled | 2.2 km |
| Solar Winschoten (H.D. Meijer Beheer) | Power plant | 2.32 MW | Operating | 2.3 km |
| Solar Winschoten (Green Box Computing) | Power plant | 2.37 MW | Operating | 2.4 km |
| 110 kV Winschoten | Substation | — | — | 2.8 km |
| 110 kV Scheemda De Eeker | Substation | — | — | 9.4 km |
| Green gas Nieuwolda (BIO Deeterink) | CO2 emitter | — | Permitted | 9.7 km |
| 380 kV Meeden | Substation | — | — | 9.8 km |
| Biomass heat Veendam (Kanadevia Inova Biogas Veendam) | CO2 emitter | — | Operating | 13 km |
| Datacenter Groningen | Data center | — | — | 15 km |
Place
Other permit notices in Groningen
- Battery storage omgevingsvergunning application, Groningen (gmb-2025-1821)
- Battery storage omgevingsvergunning application, Groningen (gmb-2025-346281)
- Battery storage omgevingsvergunning application, Groningen (gmb-2025-72161)
- Battery storage omgevingsvergunning application, Groningen (gmb-2026-411856)
- Battery storage omgevingsvergunning application, Het Hogeland (gmb-2025-285174)
- Battery storage omgevingsvergunning application, Midden-Groningen (gmb-2026-207772)
- Battery storage omgevingsvergunning application, Midden-Groningen (gmb-2026-302173)
- Battery storage omgevingsvergunning application, Oldambt (gmb-2025-500864)
Data on this page
- Officiële Bekendmakingen. Officiële Bekendmakingen, CC0 1.0.
- © OpenStreetMap contributors. OpenStreetMap data centers, ODbL 1.0.
- OpenStreetMap power infrastructure (Overpass). OpenStreetMap power infrastructure (Overpass), ODbL 1.0, © OpenStreetMap contributors.