Permit notice · Pekela, Groningen, Netherlands
Grid connection omgevingsvergunning application, Pekela (gmb-2025-427850)
Grid connection omgevingsvergunning application, Pekela (gmb-2025-427850) is a permit notice in Pekela, Groningen, Netherlands, published 3 Oct 2025.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Pekela | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Permit date | 3 Oct 2025 (omgevingsvergunning) | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Notice type | Application | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Technology | Grid connection | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Coordinates | 53.0736, 6.9612 | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
Research on this permit notice and its holder.Who holds it up to the parent company, the decision and the asset it is for, and an introduction to the holder.
Request researchLatest events
Dated events about this permit notice from official notices and registers, newest first. All recent changes.
- Permit applied for (environmental permit) · source
Nearby
Within 50 km of this permit notice: 312 power plants (249 operating, 10,139 MW), 139 substations, 26 CO2 emitters (15 operating) and 8 data centers, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Solar Nieuwe Pekela (BEE Greenlight Ommelanderwijk) | Power plant | 6.06 MW | Operating | 1.6 km |
| 110 kV Veendam Zuidwending | Substation | — | — | 2.0 km |
| Solar Veendam (EnergyStock) | Power plant | 2.94 MW | Operating | 2.4 km |
| Zonnepark Doorsneeweg | Power plant | 1.65 MW | Operating | 2.4 km |
| 110 kV substation (OSM way/1387507147) | Substation | — | — | 5.1 km |
| 380 kV Meeden | Substation | — | — | 5.6 km |
| Biomass heat Veendam (Kanadevia Inova Biogas Veendam) | CO2 emitter | — | Operating | 6.9 km |
| Electric boiler Gasselternijveen (Coöperatie Avebe) | CO2 emitter | — | Operating | 11 km |
| Datacenter Groningen | Data center | — | — | 12 km |
Place
Other permit notices in Groningen
- Battery storage omgevingsvergunning application, Groningen (gmb-2025-1821)
- Battery storage omgevingsvergunning application, Groningen (gmb-2025-346281)
- Battery storage omgevingsvergunning application, Groningen (gmb-2025-72161)
- Battery storage omgevingsvergunning application, Groningen (gmb-2026-411856)
- Battery storage omgevingsvergunning application, Het Hogeland (gmb-2025-285174)
- Battery storage omgevingsvergunning application, Midden-Groningen (gmb-2026-207772)
- Battery storage omgevingsvergunning application, Midden-Groningen (gmb-2026-302173)
- Battery storage omgevingsvergunning application, Oldambt (gmb-2025-500864)
Data on this page
- Officiële Bekendmakingen. Officiële Bekendmakingen, CC0 1.0.
- © OpenStreetMap contributors. OpenStreetMap data centers, ODbL 1.0.
- OpenStreetMap power infrastructure (Overpass). OpenStreetMap power infrastructure (Overpass), ODbL 1.0, © OpenStreetMap contributors.
- RVO SDE(+)(+) projecten in beheer and SDE viewer. RVO SDE(+)(+) projecten in beheer and SDE viewer, Free reuse, no attribution required.