Permit notice · Lochem, Gelderland, Netherlands
Solar park omgevingsvergunning decision (refused), Lochem (gmb-2025-362832)
Solar park omgevingsvergunning decision (refused), Lochem (gmb-2025-362832) is a permit notice in Lochem, Gelderland, Netherlands, published 27 Aug 2025.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Lochem | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Permit date | 27 Aug 2025 (omgevingsvergunning) | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Notice type | Decision (refused) | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Technology | Solar | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Coordinates | 52.2196, 6.2846 | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
Research on this permit notice and its applicant.Who is behind it up to the parent company, the decision and the asset it is for, and an introduction to the applicant.
Request researchLatest events
Dated events about this permit notice from official notices and registers, newest first. All recent changes.
- Permit refused (environmental permit) · source
Nearby
Within 50 km of this permit notice: 381 power plants (298 operating, 2,518 MW), 98 substations, 32 CO2 emitters (25 operating), 7 data centers and 1 processing plant, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Solar Gorssel (Zonnig Lochem) | Power plant | 12.8 MW | Operating | 5.0 km |
| Solar Deventer (ALDI Deventer) | Power plant | 3.71 MW | Operating | 5.5 km |
| Solar Deventer (Eneco Solar) | Power plant | 1.1 MW | Cancelled | 5.5 km |
| 110 kV Deventer Bergweide | Substation | — | — | 7.1 km |
| 150 kV Zutphen | Substation | — | — | 9.0 km |
| 150 kV Lochem | Substation | — | — | 9.2 km |
| Green gas Wilp Gld (Attero) | CO2 emitter | — | Operating | 14 km |
| Biomass heat Steenderen (Aviko) | CO2 emitter | — | Operating | 17 km |
| Heat pump Apeldoorn (Ameco) | CO2 emitter | — | Operating | 17 km |
Place
Other permit notices in Gelderland
- Battery storage omgevingsplan application, Nijmegen (gmb-2025-229302)
- Battery storage omgevingsplan application, Putten (gmb-2026-343049)
- Battery storage omgevingsplan application, West Betuwe (gmb-2025-12037)
- Battery storage omgevingsplan application, West Betuwe (gmb-2026-231801)
- Battery storage omgevingsplan decision, West Betuwe (gmb-2025-88274)
- Battery storage omgevingsplan decision, West Betuwe (gmb-2026-333911)
- Battery storage omgevingsvergunning application, Apeldoorn (gmb-2025-455371)
- Battery storage omgevingsvergunning application, Apeldoorn (gmb-2025-487942)
Data on this page
- Officiële Bekendmakingen. Officiële Bekendmakingen, CC0 1.0.
- OpenStreetMap power infrastructure (Overpass). OpenStreetMap power infrastructure (Overpass), ODbL 1.0, © OpenStreetMap contributors.
- RVO SDE(+)(+) projecten in beheer and SDE viewer. RVO SDE(+)(+) projecten in beheer and SDE viewer, Free reuse, no attribution required.