Renewable fuel plant · Voorst, Gelderland, Netherlands
Green gas Wilp Gld (Attero)
Green gas Wilp Gld (Attero) is a renewable fuel plant in Voorst, Gelderland, Netherlands, with 5.86 MW of capacity, operated by Attero B.V.
We hold more on this renewable fuel plant.Grid operator: available on request.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Voorst | RVO SDE(+)(+) projecten in beheer and SDE viewer · Free reuse, no attribution required · checked 25 Oct 2026 |
| Grid area | Available on request | Netbeheer Nederland capaciteitskaart · Restricted · checked 25 Oct 2026 |
| Address | Sluinerweg 12, 7384 SC Wilp Gld | RVO SDE(+)(+) projecten in beheer and SDE viewer · Free reuse, no attribution required · checked 25 Oct 2026 |
| Status | Operating | RVO SDE(+)(+) projecten in beheer and SDE viewer · Free reuse, no attribution required · checked 25 Oct 2026 |
| Start year | 2022 | RVO SDE(+)(+) projecten in beheer and SDE viewer · Free reuse, no attribution required · checked 25 Oct 2026 |
| Operator | Attero B.V. | RVO SDE(+)(+) projecten in beheer and SDE viewer · Free reuse, no attribution required · checked 25 Oct 2026 |
| Capacity | 5.86 MW | RVO SDE(+)(+) projecten in beheer and SDE viewer · Free reuse, no attribution required · checked 25 Oct 2026 |
| Technology | Green gas | RVO SDE(+)(+) projecten in beheer and SDE viewer · Free reuse, no attribution required · checked 25 Oct 2026 |
| Grid operator | Available on request | Netbeheer Nederland capaciteitskaart · Restricted · checked 25 Oct 2026 |
| Coordinates | 52.2018, 6.0777 | RVO SDE(+)(+) projecten in beheer and SDE viewer · Free reuse, no attribution required · checked 25 Oct 2026 |
Know more about this renewable fuel plant, or want an introduction to its operator? Ask us.
How it compares
Green gas Wilp Gld (Attero) is the 4th-largest of 6 renewable fuel plants in Gelderland and the 34th-largest of 56 in the Netherlands by capacity; its 5.86 MW is 1% of the 584 MW we hold for the Netherlands. Ranks and totals cover the renewable fuel plants in our data that report their capacity, not every one in existence. Renewable fuel plants planned, permitted or under construction are ranked apart.
| Within | Rank | Total | Share |
|---|---|---|---|
| Gelderland | 4th of 6 | 41.5 MW | 14% |
| Netherlands | 34th of 56 | 584 MW | 1% |
Nearby
Within 50 km of this renewable fuel plant: 1,054 permit notices, 447 power plants (354 operating, 3,720 MW), 102 substations, 29 heat plants (16 operating, 68.9 MW), 8 data centers and 1 processing plant, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Biomass Wilp Gld (Attero) | Power plant | 2 MW | Operating | 0.0 km |
| Solar Wilp Gld (Attero) | Power plant | 1.93 MW | Planned | 0.0 km |
| Solar Klarenbeek (KS NL15) | Power plant | 13 MW | Operating | 0.6 km |
| Nitrogen natuurvergunning decision, Voorst (prb-2025-18328) | Permit notice | — | — | 1.1 km |
| Nitrogen natuurvergunning draft decision, Voorst (prb-2025-15161) | Permit notice | — | — | 1.1 km |
| Nitrogen natuurvergunning draft decision, Voorst (prb-2026-15089) | Permit notice | — | — | 1.3 km |
| 150 kV Woudhuis | Substation | — | — | 3.0 km |
| Heat pump Apeldoorn (Ameco) | Heat plant | 1.26 MW | Operating | 3.2 km |
| Heat pump Apeldoorn (Esa) | Heat plant | 1.1 MW | Operating | 6.5 km |
Operator and place
More from Attero B.V.
- Green gas Wijster (Attero)17.3 MW
- Green gas Tilburg (Attero)7.32 MW
- Green gas Tilburg (Attero)7.32 MW · permitted
- Green gas Groningen (Attero)6.84 MW
- Green gas Wijster (Attero)3.34 MW · permitted
- Waste incineration Wijster (Attero)92.3 MW
- Solar Tilburg (Attero)23.5 MW
- Biomass heat Odiliapeel (Attero)8.21 MW
Other renewable fuel plants in Gelderland
- Green gas Beltrum (Groot Zevert Vergisting)9.77 MW
- Green gas Harderwijk (BMP Harderwijk)9.77 MW
- Green gas Bemmel (Groen Gas Gelderland)9.57 MW
- Green gas Weurt (ARN)3.42 MW
- Green gas Lichtenvoorde (Biologische Industriële Reststoffenverwerking)3.15 MW
- Green gas Lichtenvoorde (Biologische Industriële Reststoffenverwerking)4.6 MW · permitted
- Green gas Weurt (Arn)4.4 MW · permitted
- Green gas Bemmel (Groen Gas Gelderland)3.13 MW · permitted
Data on this page
- Netbeheer Nederland capaciteitskaart. Netbeheer Nederland capaciteitskaart, Restricted.
- Officiële Bekendmakingen. Officiële Bekendmakingen, CC0 1.0.
- OpenStreetMap power infrastructure (Overpass). OpenStreetMap power infrastructure (Overpass), ODbL 1.0, © OpenStreetMap contributors.
- RVO SDE(+)(+) projecten in beheer and SDE viewer. RVO SDE(+)(+) projecten in beheer and SDE viewer, Free reuse, no attribution required.