Permit notice · Epe, Gelderland, Netherlands

Nitrogen natuurvergunning draft decision, Epe (prb-2026-12062)

Nitrogen natuurvergunning draft decision, Epe (prb-2026-12062) is a permit notice in Epe, Gelderland, Netherlands, published 15 Jul 2026.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationEpeOfficiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026
Permit date15 Jul 2026 (natuurvergunning)Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026
Notice typeDraft decisionOfficiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026
TechnologyNitrogenOfficiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026
Coordinates52.3599, 6.0170Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026

Research on this permit notice and its holder.Who holds it up to the parent company, the decision and the asset it is for, and an introduction to the holder.

Request research

Latest events

Dated events about this permit notice from official notices and registers, newest first. All recent changes.

  1. Draft decision (nature permit) · source

Nearby

Within 50 km of this permit notice: 403 power plants (322 operating, 4,807 MW), 81 substations, 46 CO2 emitters (33 operating), 9 data centers and 1 processing plant, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Zonnepark De HorstPower plant14.4 MWPermitted6.2 km
150 kV VaassenSubstation——6.4 km
Zonnepark HeerderstrandPower plant2.55 MWPlanned7.0 km
Solar Olst (IJssellandschap)Power plant2.65 MWOperating7.2 km
110 kV OlstSubstation——7.4 km
150 kV HattemSubstation——11 km
Kolo NL3 ApeldoornData center——13 km
Biomass heat Apeldoorn (Ennatuurlijk Warmteproductie & Assets)CO2 emitter—Operating14 km
Equinix Zwolle ZW1Data center——17 km

Place

Other permit notices in Gelderland

All 948 permit notices in Gelderland, Netherlands

Data on this page