Permit notice · Barneveld, Gelderland, Netherlands
Nitrogen natuurvergunning draft decision, Barneveld (prb-2025-13092)
Nitrogen natuurvergunning draft decision, Barneveld (prb-2025-13092) is a permit notice in Barneveld, Gelderland, Netherlands, published 11 Aug 2025.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Barneveld | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Permit date | 11 Aug 2025 (natuurvergunning) | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Notice type | Draft decision | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Technology | Nitrogen | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
| Coordinates | 52.1693, 5.6865 | Officiële Bekendmakingen · record · CC0 1.0 · checked 24 Oct 2026 |
Research on this permit notice and its holder.Who holds it up to the parent company, the decision and the asset it is for, and an introduction to the holder.
Request researchLatest events
Dated events about this permit notice from official notices and registers, newest first. All recent changes.
- Draft decision (nature permit) · source
Nearby
Within 50 km of this permit notice: 491 power plants (381 operating, 6,151 MW), 90 substations, 47 CO2 emitters (27 operating), 12 data centers and 1 processing plant, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Solar Voorthuizen (Denkavit Nederland) | Power plant | 2.23 MW | Operating | 3.1 km |
| Zonnepark Branderwal | Power plant | 28.4 MW | Operating | 3.5 km |
| Solar Barneveld (BPN) | Power plant | 5.52 MW | Operating | 4.3 km |
| 150 kV Harselaar | Substation | — | — | 4.5 km |
| Biomass heat Nijkerk Gld (Den Akker Pluimvee) | CO2 emitter | — | Operating | 8.7 km |
| 150 kV Ede | Substation | — | — | 13 km |
| Cellnex | Data center | — | — | 14 km |
| Residual heat Ede Gld (Bio-Energie De Vallei) | CO2 emitter | — | Cancelled | 15 km |
| BIT-1 Datacenter | Data center | — | — | 16 km |
Place
Other permit notices in Gelderland
- Battery storage omgevingsplan application, Nijmegen (gmb-2025-229302)
- Battery storage omgevingsplan application, Putten (gmb-2026-343049)
- Battery storage omgevingsplan application, West Betuwe (gmb-2025-12037)
- Battery storage omgevingsplan application, West Betuwe (gmb-2026-231801)
- Battery storage omgevingsplan decision, West Betuwe (gmb-2025-88274)
- Battery storage omgevingsplan decision, West Betuwe (gmb-2026-333911)
- Battery storage omgevingsvergunning application, Apeldoorn (gmb-2025-455371)
- Battery storage omgevingsvergunning application, Apeldoorn (gmb-2025-487942)
Data on this page
- Officiële Bekendmakingen. Officiële Bekendmakingen, CC0 1.0.
- © OpenStreetMap contributors. OpenStreetMap data centers, ODbL 1.0.
- OpenStreetMap power infrastructure (Overpass). OpenStreetMap power infrastructure (Overpass), ODbL 1.0, © OpenStreetMap contributors.
- RVO SDE(+)(+) projecten in beheer and SDE viewer. RVO SDE(+)(+) projecten in beheer and SDE viewer, Free reuse, no attribution required.